|
Washington Winners
Best Public Project
Seattle Central Library
Owner: Seattle Public Library
Submitted by: by Hoffman Construction Co., Seattle
Architect: OM U.S. A. and LMN Architects, Seattle
Structural, Mechanical and Electrical Engineer: ARUP, Los
Angeles, Calif.
Structural/Civil Engineer: Magnusson Klemencic Associates
Major subcontractors: McKinstry, Cochran Electric, The Erection
Co., W.A. Botting Co.,; Long Painting, Seattle, and R.H. Rhine
Co.
Completed in the spring of 2004, the Seattle Central Library
has quickly become the most recognized structure in the downtown
core.
The 412,000-sq.-ft. 11-story building is divided into five
distinct platforms offset from each other and designed to
resemble a stack of books. Each platform offers a different
service. An all-encompassing curtain wall visually pulls together
the entire building. The library has received outstanding
public support and been reviewed in numerous architecture
publications.
Construction of a building with offset levels that cantilever
out at varying degrees and angles was more difficult than
the typical office building. To support the offset platforms
and prevent the building from toppling over, a nontraditional
support was needed. Opposing sliced steel box columns set
at critical angles and areas throughout the building serve
as support for the structure.
To offset the platforms during construction, Hoffman devised
a temporary system that would hold the structure in place
until the building's structural steel system was complete.
Three hundred tons of steel, later recycled, was used to construct
the temporary support system.
Hoffman took a proactive approach to addressing potential
setbacks when installing the curtain-wall system. The glass
system came from Germany, with fasteners and connection points
already installed. Tolerances were tight, allowing little
wiggle room.
Using a special surveying system that scanned the surface
of the library's steel grid,
crews were able to pinpoint the precise location of each connection
point.
Moving thousands of books into the new library greatly concerned
the owner. To make sure construction kept pace with the planned
move, Hoffman regularly attended moving meetings to keep abreast
of the owner's concerns.
Best Public Project
Honorable Mention
Sea-Tac Airport Concourse A
Owner: Port of Seattle
Submitted by: Clark Construction Group, Calif.
Architect: NBBJ
Engineer: Wood Harbinger/CDI
Major subcontractors: Valley Electric Co.; University Mechanical
Contractors; Seimens, Pacific Construction Systems; G&T
Conveyor, Conco Cement Co.
At the time of the terrorist attacks, over 20 percent of
the construction was completed. New design elements, adding
$50 million to the construction cost, had to be added because
of security concerns. In an effort to minimize the impacts
on the project schedule, the Port of Seattle, designers, Clark
and the baggage handler G&T Conveyor developed a collaborative
plan to fast track the process.
Best Mechanical Project
Sea-Tac
Airport Concourse A
Owner: Port of Seattle
Submitted by: University Mechanical Contractors, Seattle
Architect: NBBJ, Seattle
Engineer: Wood Harbinger/CDI, Seattle
Major subcontractors: Valley Electric Co., Everett, Wash.,
electrical; University Mechanical Contractors, Seattle; mechanical;
Seimens, Bellevue, Wash., building controls; Pacific Construction
Systems, Tacoma, Wash., drywall; G&T Conveyor, Seatac,
Wash., baggage handling system; Conco Cement Co., Kent, concrete.
The 870,000-sq.-ft. South Terminal Expansion Project provides
Sea-Tac Terminal with new ticketing areas, 14 passenger gates,
an expanded baggage claim area and five levels of office space.
University Mechanical performed complete mechanical for the
project except for fire protection and DDC controls.
One of the obvious challenges of Sea-Tac was the Sept. 11
attacks, which occurred in the middle of the construction
schedule. New security measures were enforced, and immediate
system changes were required for areas such as baggage handling.
UMC's goal was to be as flexible and proactive as possible
to keep the project on schedule and to assist with design
modifications.
The judges were particularly impressed with the difficulty
of the shutdowns necessary to accommodate utility tie-ins.
Because of the enormous size and amount of pipe, complex welds
and the refill time required for up to 100,000 gallons, the
shutdowns were a tremendous challenge.
Another example was installing the piping. This part of the
project took more than 16,000 hours, even with careful preplanning,
fabrication and coordination. UMC installed over 32 mi. of
pipe, 975 pieces of equipment, 29 large air-handling units
and 480 plumbing fixtures.
Best Electrical Project
Seattle Biomedical Research Institute
Submitted by: Sparling, Seattle
Seattle Biomedical Research Institute is the Northwest's
premier research lab for research on infectious diseases.
Located at South Lake Union, near the downtown core, the 112,000-sq.-ft.
building opened in March.
Sparling's design was key in solving critical problems that
could affect the lab experiments and health of safety of workers.
The first goal of the design was to eliminate outages, surges
and sags in the electrical system. One extended power outage
could cost millions of dollars in lost research. An emergency
generator in the labs provides back up for fume hoods, refrigerators,
and some incubators.
The project was on a fast-track design with the tenant improvement
design coinciding with construction of the building's core
and shell. Weekly evaluation of schedules and ongoing communication
with multiple users helped lead to two floors of lab space.
Because Seattle Biomed intends to capture LEED status, exterior
lighting was a major concern. According to the requirements,
no lighting can go beyond the property line, but the building
backs up to an unlit alley - dangerous for security reasons.
Sparling developed a lighting system that illuminates the
right-of-way but not the adjacent properties. Sparling reduced
energy use by 30 percent overall.
Best Engineering Project
Sacred
Heart Hospital, Spokane
Submitted by Coffman Engineers, Spokane
Health-care facilities represent a special engineering niche,
due to unique technological, administrative, end user and
regulatory needs.
Coffman Engineers designed a 235,000-sq.-ft. addition coupled
with an 88,500-sq.-ft. remodel for Sacred Heart Hospital in
Spokane. Interesting features of the project include: Three
of the seven stories of the addition are partially built over
a city arterial road; one of the new building stories is built
atop the existing hospital; and the site is primarily rock
substrate, which required blasting to excavate for the basement
level.
The building is cast-in-place concrete with concrete shear
walls in order to minimize building vibrations. The software
RAM Steel was used to design the composite-beam floor systems
for the floors over the city street, with special attention
to the vibration characteristics of the surgery floors.
The contract cost for this project was $100 million, and
the contractor was able to finish two months ahead of schedule
and under budget by $2 million. The energy savings on the
project netted the owner $168,000 in savings this year.
Best Architecture
Tashiro
Kaplan Lofts
Owner: Artspace Projects
Submitted by: Stickney Murphy Romine Architects
General Contractor: Marpac Construction
Electrical Engineer: Atkinson & Associates; Structural
Engineer, Coughlin Porter Lundeen, sider & Beyers Associates,
mechanical
Major Subcontractors: Puget Sound Masonry; Snyder Roofing;
D. W. Close
The Tashiro Kaplan Artist Lofts is a mixed-use project providing
arts-related commercial space and 50 permanent affordable,
live/work residential spaces. Located in Seattle's Pioneer
Square Historic Preservation District, the project occupies
all of an oddly shaped city block.
Construction work on the building was complex. The buildings
occupied 100 percent of the site, leaving no space for staging.
Hazardous material abatement included asbestos insulation,
tile and roofing and multiple layers of lead paint on the
exterior terra cotta.
The design addition had to meet the requirements of the Pioneer
Square Preservation Board. This was accomplished by expanding
the columnar rhythm of the existing Kaplan building and maintaining
the juxtaposition of glass to wall on the exterior.
The structural upgrade to the building included large steel
brace frames to absorb the lateral loads that may occur during
an earthquake. Usually these would be placed on the building
exterior, but preservation guidelines prohibited this.
Instead, the bracing had to be placed on the building interior,
one bay to the interior of the window wall. The frames were
left exposed in the unit interiors and were designed to add
an industrial aesthetic to the lofts located on the third
floor.
The original wood storefronts underwent extensive restoration
and/or replication, maintaining the large areas of glass needed
for galleries and arts-related businesses. Three floors of
wood-frame construction were placed on a new 10-in., two-way
concrete transfer slab located on the old concrete roof structure.
Best Private Project
Alcyone
Apartments
Submitted by: Rushforth Construction
Owner: Alcyone
Archtiect: GGLO
Structural Engineer: Magnusson Klemencic Assoicates
Major Subcontractors, Donald B Murphy Contractors, Roy Freeman
Roofing Co., One Way Plumbing; Air Systems Inc.
The Alcyone Apartments is a 162-unit market rate apartment
building, located near downtown Seattle.
It is one of the first multifamily structures of this scale
to use metal-stud construction in Seattle. The construction
type was chosen to further the owner's sustainability goals.
The light-gauge steel contractor failed early on in the project,
and Rushforth crews had to compete the framing and coordinate
deliveries out of the light-gauge steel manufacturer in Bend,
Ore. Rushforth ran between two and three trips per week for
deliveries.
Keeping neighbors informed of monthly construction activities
was an important part of the project. During project planning,
the design team and the owner met numerous times with the
Cascade Neighborhood Council to mitigate impact of the building
on Cascade Park and the Pea Patch.
The judges were impressed with Rushforth's ability to keep
on track with the building, even after a major subcontractor
was unavailable.
Best Public/Private Project
Northwest Detention Center
Owner: CSC of Tacoma
Submitted by: Lydig Construction
Architect: Hok Associates with Burgess Weaver Design Group
General Contractor: Dinosaur Valley Construction/Lydig Construction
Consultants: David Evans & Associates, Rupert Engineering
Major subcontractors: Auburn Mechanical; Berg Electric; MacDonald
Miller Facility Solutions.
Located near the Port of Tacoma, the building was designed
for Immigration and Naturalization and Homeland Security purposes.
The project originally had a 12-month schedule, but two months
were cut because of financial problems. Unusual scheduling,
including constructing the building shell before the slabs
were poured help keep the project on schedule.
Best Private Project
Honorable Mention
MultiCare Medical Center addition,
Tacoma
Submitted by: Skanska USA Building, Seattle
Owner: MultiCare Health System
Architect: Giffin Bolte Jurgens Architects
Structural Engineer: Putnam Collins Scott and Associates
Mechanical Engineer: Bouillon EngineeringMajor Subcontractors:
Cochran Electric, Hermanson Co., Nuprecon Inc., R. W. Rhine;
Stirrett Johnsen; Ralph's Concrete Pumping
Innovative construction techniques and creative scheduling
processes allowed Skanska USA Building to add four stories
atop a busy hospital without disrupting critical functions.
The $43 million addition to MultiCare Medical Centers L wing
expands the facility space by 176,000 sq. ft. and houses a
surgery department, vascular/heart surgery center, CATH labs
and future build-out space.
Before work could start, Skanska had to augment the existing
structural system to support the new construction. Crews executed
the work from inside the building, staging equipment in the
hospital's basement and drilling piers 45 ft. deep beneath
the existing general services department.
Holes were cut in the existing second-floor slab and concrete
was pumped through a slick line for the drilled piers, shear
walls and pile caps. Performing this work from outside the
building would have impacted access to the emergency department,
required a costly shoring system, and required the relocation
of major utilities. The addition sits on top of the fourth-floor
lab that functions 24 hours per day, seven days per week,
serving the entire MultiCare system. By scheduling work at
night, crews completed several parts of the project without
affecting the lab staff.
Skanska punched two elevator shafts through the lab floor,
partitioning off construction areas, weatherproofing holes
from the outside and bringing in steel in small pieces. Pipe
conduit and other systems were prefabricated as much as possible
to minimize excessive building activity and keep disruptions
to a minimum.
The seventh-floor addition houses a state-of-the-art cardiovascular
surgery center. Many of the center's systems such as lighting
and temperature control are activated by voice. A significant
amount of mechanical, electrical and cabling systems had to
be installed in the ceiling, requiring intense coordination
with the trades.
Best Renovation
King
County Courthouse
Owner's Representative: The Seneca Group
Submitted by Skanska USA Building
Architect: Stickney Murphy Romine
Structural Engineer: Coughlin Porter Lundeen
Major Subcontractors: Cochran Electric, Brundage Bone Concrete
Pumping; Hermanson Co., Long Painting, Snyder Roofing,
The renovation of the King County Courthouse encompasses
all aspects of a challenging job, including an occupied space
and a tight budget, limited area for equipment and materials
and a schedule that could not be adjusted.
Skanska addressed each challenge head-on, shaving five months
off the original 27-month schedule and slashing $8 million
from the construction budget.
The $78 million two-year renovation of the 90-year-old courthouse
called for extensive structural seismic upgrades along with
fire and life safety improvements. The courthouse remained
occupied and functioning.
Court proceedings continued for the duration of the project,
and crews were required to stop work if courtroom officials
requested silence. As a result, much of the work was completed
at night. A task as simple as testing the fire alarms with
city officials took as long as two weeks.
A significant overhang at the top of the building prohibited
the tower crane from delivering materials within 6-ft. feet
of the building. Skanska fashioned a picking boom with a trolley
to shuttle 1,000 tons of steel into the building.
Once the steel was inside, it was moved without the use of
a crane, even pieces as large as 6,000 lbs. Skanska shortened
the project calendar by five months. Crews worked two 10-hour
shifts per day, four days per week. This decision, along with
extensive value engineering, saved the county $8 million.
Even with more than 750,000 hours of work in a 22-month period,
no serious time-loss accidents occurred.
Best Renovation
Honorable Mention
Washington
State Legislative Building
Owner: State of Washington
Submitted by: Mortensen, Seattle
Fitting modern systems into a historic building was what
this project was all about.
To make the building functional for the next 75 years, the
entire building infrastructure needed to be replaced and new
systems added (data, fire, alarm and protection, wireless).
All this had to be done while maintaining the basic construction
and original beauty of this National Historic Building, built
in 1899. The quality of construction is unequalled. Mortensen
replace wood wainscot, plaster cornices, exterior stonework
and Alaskan Tokeen Marble with the same methods used in the
late 19th Century. Planning and locating materials took months.
Historic elements were protected during construction with
OSB board panels. The temporary walls were then donated to
Habitat for Humanity for use in homes.
Early in the preconstruction phase the Nisqually Earthquake
occurred, requiring immediate changes that turned a six-year
project in an occupied building to a three-year project in
an empty building.
All data banks, phone systems and security systems had to
be operational 24 hours per day, seven days a week. This meant
concurrent systems had to be constructed and tied into existing
systems with little delay. Security systems were completely
overhauled after Sept. 11.
More hazardous materials were encountered than anticipated.
Newly discovered hazardous materials were disposed of properly
with little impact to the project schedule.
Best Renovation
Honorable Mention
Patsy Clark Mansion
Submitted by: Steve Walker Construction, Spokane
Owner: Eymann, Allison, Fennessey, Hunter, Jones, P.S.
Architect: Northwest Architectural Co.
Major Subcontractors: Jim Kolva Associates, Landscape Designs
by /Suzanne
Snowdon, Stevens Creek Construction, Inland Fixture Co., Rymn
House Stained Glass, St. Joseph's Wood Floors,
The restoration of a 100-year-old building into an up-to-date
office provided numerous challenges.
The cantilevered mezzanine was sagging due to incorrect installation.
Because of the historic golf leaf, plaster and hand-carved
beams, contractors removed the flooring and installed supports
from above. Much of the work was hand done, rather than using
prefabricated materials
Editor's Choice
House
of Knowledge
Submitted by: Synergy Construction
Owner Port Gamble S'Klallam Tribe
Major Subcontractors: Alpine Development, B & B Painting;
Heins Concrete Construction; Robs Electric Inc., Swift Plumbing
and Heating, Timberwolf Woodworks.
The House of Knowledge is a vision of the Port Gamble S'Klallam
people. It is a village of learning composed of a longhouse,
a career and education department and elder center, a wood-carving
workshop and a new library.
The most difficult part of the project was finding a subcontractor
familiar with log pole construction. Synergy interviewed 16
firms with bids between $100,000 and $750,000.
The
project had a tight budget, so Synergy considered its options
carefully and finally chose a subcontractor who could meet
the owner's budget.
The interior of the building is completely exposed framing
that requires all of the fastening systems to be invisible.
The end result is a longhouse resembling early 1900s construction
with modern-day engineering.
Synergy maintained a high safety rating throughout the project
by holding early meetings with subcontractors to discuss their
site-specific safety plans.
Click here for the list
of Oregon Winners
|