|
PUBLIC INFRASTRUCTURE PROJECT
Award of Excellence
(tie)
|
|
Newport Wastewater Treatment
Plant
Photo courtesy ofSlayden
Construction
|
Newport Wastewater Treatment
Plant, Newport, Ore.
Submitted by: Slayden Construction, Stayton, Ore.
The Newport Wastewater Treatment Plant was a
2-1/2 year, $22.6 million project that essentially replaced
the City of Newport's outdated plant with a state-of-the-art
facility located in a remote hilly area east of South Beach.
The facility, built by Slayden and designed by Fuller and
Morris Engineers with assistance from CH2MHill, utilized an
innovative treatment process provided by US Filter for the
liquids steam treatment as well as a Class IV biosolids treatment
facility.
The project consisted of 9,000 cu. yds. of cast-in-place
concrete, massive site excavation, and extensive mechanical
and electrical systems inherent in a large treatment plant.
The project overcame the challenge of relentless rainfall
as well as tying together a fiber optic network connecting
more than a dozen points throughout the city.
The engineering decision to place twin 24-in. directionally
drilled pipelines 3,000 ft. under Yaquina Bay was also a unique
solution to convey the raw sewage and the treated effluent
from one side of the bay to the other. This eliminated long
pipeline runs around the bay and solved the problem of having
to run the pipes on the Yaquina Bay Bridge, as both scenarios
presented impassable roadblocks.
AND
PUBLIC INFRASTRUCTURE
PROJECT
Award
of Excellence (tie)
Klamath Falls A-Canal Fish Screen,
Klamath Falls, Ore.
Submitted by: Slayden Construction, Stayton, Ore.
The Klamath Falls A-Canal Fish Screen project was built at
the bottom end of Klamath Lake to screen endangered sucker
fish from being brought into the irrigation canal that feeds
water to the entire farming community. The need for the project
arose in the summer of 2001 when the Bureau of Reclamation
shut the headgates that control water to the irrigation canal
to protect the fish. This caused an uproar in the farming
community and resulted in the need for an emergency solution.
At the end of irrigation season in October 2002, a cofferdam
was built to dry out the irrigation canal for construction.
The original headgates were demolished and 25,000 cu. yds.
of soil were excavated in order to construction the 550 ft.
long by 60 ft. wide screening canal. At the top of the canal,
a gripper rake periodically cleans a metal trash rack that
prevents anything larger than two inches in diameter from
entering the canal. Next, full-height, stainless steel fish
screens prevent the passage of anything larger than a dime.
These screens filter fish into a pump station, where they
are then pumped back into Klamath Lake through an evaluation
station. This station has an open canal, nets and an overhead
bridge crane. The station allows biologists check the size,
number and health of any fish in the canal.
The canal outage limitation meant Slayden had less than
six months to complete the reconstruction of the A-Canal.
Flows were cut off October 15, 2002, and in less than six
months - on April 1, 2003 - the headgates were opened and
have been running ever since. Despite snow and below-freezing
temperatures, crews were able to place 6,000 cu. yds. of concrete
- completing a concrete pour every day for six weeks.
"To complete this project within schedule and work
with the environmental and usability issues is truly outstanding,"
one jury member commented.
PUBLIC PROJECT- LARGE
Honorable
Mention
Autzen Stadium Expansion - University
of Oregon, Eugene, Ore.
Submitted by: Hunt Construction Group, Indianapolis, Ind.
The expansion of Autzen Stadium on the University of Oregon
campus included the addition of 12,500 seats (for a total
of 55,500 seats), renovation and expansion of the existing
seating bowl, 32 high-end suites, a new main concourse and
a club lounge featuring 22,000 sq. ft. of amenities.
The $80 million project was constructed in a breakneck nine
month timeframe between football seasons, while projects similar
in nature take 18 to 24 months to build. This accelerated
delivery method allowed the university the luxury of never
missing a home game at Autzen.
The challenge of the short construction schedule -- which
was shortened another two weeks during construction due to
Pac 10 game schedules - was overcome through creative bid
package designs, procurement and intense scheduling.
"Not only were they building a complex project, but
they were doing it within an occupied campus," noted
one juror.
The design and construction of the seating bowl was another
impressive element of the Autzen Stadium expansion project.
The architectural design needed to stress expansion, yet be
bold and original. One facet of this innovation is the usage
of precast "Y" columns to support the upper bowl.
These columns were erected and assembled using splice sleeves
and Dywidag bars that were grouted. Additionally, the upper
bowl precast utilized post-tensioning raker sections and 24-in.
pipe struts that allowed for fewer structural steel members
yet still meet the high seismic demands of the specifications.
PUBLIC PROJECT-
SMALL
Award of Excellence
|
|
Helen Gordon Child Development
Center
Photo by pazdesigngroup.com
|
Helen Gordon Child Development Center,
Portland, Ore.
Submitted by: LCG Pence, Portland, Ore.
The team tasked with the expansion of the Helen Gordon Child
Development Center on the Portland State University campus
faced a tight budget and numerous changes to its original
design, yet still delivered the completed project to the owner
ahead of the original schedule.
The center - which offers early childhood education to 130
children of PSU student, faculty, staff and the community
- serves as an academic laboratory resource, inviting participation
by university faculty and students in the fields of early
childhood education, child and family studies, psychology
and related fields. The expansion consists of two levels with
a small third level and basement. The addition totals 15,500
sq. ft. The first and second floors are attached to the original
structure by two inventive configurations.
When the original bids were submitted and reviewed, it was
clear to the owners that the project was seriously over budget.
As the lowest bidder, LCG Pence knew that some drastic measures
would need to be taken to get the project off the ground.
Working with the owners and GBD Architects, the builders identified
a number of valuing engineering measures to bring the project
within budget. Interior finishes were changed from maple to
P-lam. The exterior metal siding was changed to Hardi-panel.
Most significantly, the boiler water heating system was changed
to an electric heat pump system, saving approximately $34,000.
The team made nearly $500,000 in value engineering cuts
when, well into the project, state funds became available.
The team was able to quickly shift gears and add back in some
of the original plans for the facility.
AND
PUBLIC PROJECT- SMALL
Honorable
Mention
Medford Central Library, Medford,
Ore.
Submitted by: SD Deacon, Portland, Ore.
The new 83,000-sq.-ft., two-story Medford Central Library
is not only a gathering place for the citizens in and around
Medford, but it will also provide classrooms and a reference
library for the students and faculty of Rogue Community College.
The new steel structure - with brick, ground-faced CMU,
composite metal panels and aluminum storefront exterior finishes
- will replace the current, 90 year old facility which is
crowded and unable to expand. It will also bring under one
roof all administrative functions - currently spread across
three buildings - for the 15 branches of the Jackson County
library system.
Innovative construction techniques include the use of self-compacting
concrete for the building's shear walls. Use of this type
of concrete allowed the walls to be constructed in one continuous
pour, saving considerable time while also minimizing the amount
of rock pockets.
PRIVATE PROJECT
Award
of Excellence
|
|
|
adidas Village
Photo courtesy of R&H
Construction
|
adidas Village, Portland, Ore.
Submitted by: R&H Construction, Portland, Ore.
From building a world class headquarters building in a residential
area to transforming a 1950s hospital into usable office space,
adidas Village crews had their work cut out for them.
Located on 11 acres in North Portland, adidas Village is
a combination of a 200,000-sq.-ft. remodel of the former Bess
Kaiser Hospital, a new 900-car underground parking garage,
public plazas and park, two new office buildings and a sports
center for employees. The finished structure is home to all
adidas operations: adidas America, adidas International U.S.
office and Salomon North America.
Building in a residential area requires heightened sensitivity
to a neighborhood's concerns. From the inception, it was important
to the adidas project teams that the campus integrate into
the surrounding neighborhood. The project team conducted regular
meetings with the neighborhood association throughout the
design and construction process, giving area residents a venue
for voicing their concerns about how the project might impact
the livability of the area.
Creating a new corporate headquarters out of an existing
hospital was a challenge for the adidas team. The structure
had been compromised as a result of numerous alterations and
was in need of seismic upgrades. Crews found a few surprises
as work progressed, such as uneven floor slabs and differences
in ceiling heights.
"To convert the old hospital and match in four new
structures was a much larger task than most would take on,"
said one jury member.
On the east side of the campus, the oval Sports Center building
was difficult to lay out. The structural steel columns didn't
line up like in a square or rectangular building. One of the
job's foremen created a full-scale model of the base in a
vacant parking lot to ensure appropriate construction.
PUBLIC/PRIVATE PROJECT
Award
of Excellence
Chestnut Lane Assisted Living Facility,
Gresham, Ore.
Submitted by: Walsh Construction Co., Portland, Ore.
Crews overcame a learning curve associated with the use of
a new building material to successfully complete the Chestnut
Lane Assisted Living Facility in Gresham, Ore.
The walls of the 70-unit, 53,000-sq.-ft. assisted living
facility - specifically designed for deaf and deaf/blind residents
- were constructed using the insulated concrete form (ICF)
wall system of interlocking polystyrene forms that remain
in place after the concrete is poured. The insulating capacity
of expanded polystyrene coupled with the structural integrity
of reinforced concrete makes the walls stronger and quieter
as well as more energy efficient, cost effective and construction
efficient. Walsh Construction Company crews had never before
built a structure using the ICF system, which is relatively
new to the Portland area. The coordination of a new type of
construction also presented a learning curve for building
officials.
Other building challenges included hiding a complex HVAC
system in a webbed joist ceiling structure, coordination of
tower cranes around light rail and overhead lines, and dealing
with a limited state budget.
RENOVATION/RESTORATION
Award
of Excellence
|
|
|
adidas Village
Image courtesy of LRS
|
adidas Village, Portland, Ore.
Submitted by: LRS Architects, Portland, Ore.
While busy creating a vibrant new North American headquarters
for adidas-Salomon, project designers remained conscious of
sustainability issues throughout the remodel and building
process.
All of the existing old windows were replaced with energy
efficient glass, and the addition of variable frequency drives
was made to the HVAC system. The VFDs provide variable volume
control of existing systems to save energy during lower load
conditions. Another notable green decision was the installation
of 20-in. square (with a high recycled content) Interface
carpet tiles throughout the entire campus. Consequently, adidas
Village earned PGE's Earth Advantage designation for excellence
in energy efficiency and sustainability.
On each floor, the space was designed with open areas and
conference rooms at the building's perimeter so light could
flood the interior. Independent offices were placed within
the core areas. Given the interactive culture at adidas, the
floors in the West Village were designed to allow 900 staff
members easy access to the 27 different departments.
"The most impressive project in the group," noted
one juror, "both for its use of an existing facility
and the addition of new space. Well done."
RENOVATION/RESTORATION
Honorable
Mention
Hood River Library, Hood River, Ore.
Submitted by: Skanska USA Building, Beaverton, Ore.
The renovation of the Hood River Library combined hard, work,
dedication and significant community support, resulting in
a facility used by the entire Hood River community.
The renovation began in August 2002 and finished this July.
The project involved creating a library that is twice its
original size. Crews renovated 7,690 sq. ft. and added 10,466
sq. ft. The scope of work included seismic upgrades, site
improvements and complex mechanical and electrical upgrades
The new structure will allow for more books, more computers,
accessibility for people with disabilities and programs for
children, teens and adults.
The expansion has been designed to match the style of the
historic Jacobean building. The original landmark structure
had been constructed in 1914 through a grant from the Andrew
Carnegie Foundation and was listed on the National Historic
Registry.
"This is an outstanding example of maintaining the
historical look while providing a totally upgraded building
that meets today's standards," said one juror.
Challenges facing the construction crews included maneuvering
heavy equipment nearly up to the property line on a steep
hillside. There was a lot of tight cornering to retain the
existing trees while erecting a large building on a small
lot.
Donations from the community to the Hood River Library Foundation
to fund the project ranged from $2 to $45,000.
ARCHITECTURAL DESIGN
Award
of Excellence
|
|
10th and Mill Building
Photo courtesy of TBG Architects & Planners
|
10th and Mill Building, Eugene, Ore.
Submitted by: TBG Architects and Planners, Eugene, Ore.
The goal of the 10th and Mill Building project team was to
create and enduring work of architecture that would elevate
the downtown experience with a contemporary design set within
the framework of classical proportions. With an exterior featuring
steel and brick construction with copper and slate accents
surrounded by a number of heritage trees thoughtfully protected
during construction, it appears they have succeeded.
The efforts of the entire design and construction team resulted
in a building that exceeds the energy efficiency standards
of Oregon codes by approximately 30 percent. The HVAC system
is split with a separate rooftop unit per floor for net metering
of individual tenants to encourage energy conservation. Web-based
computer controls allow remote monitoring and adjustment for
optimum efficiency and user comfort. The system capacity was
reduced from the original design due primarily to the many
measures taken to reduce loads by maximizing daylighting throughout
the building.
Though not a traditional design-build project, regular design
meetings throughout the initial stages of the project with
all primary members of the building and design teams fostered
a collaborative and creative process that greatly benefited
the overall building design and budget. Cooperation between
the structural engineer, architect and contractor in the early
stages of the project facilitated and expedited schedule with
multiple phases which permitted the start of construction
ahead of schedule, shortened the overall building period and
minimized impact on the surrounding neighbors.
"This building shows respect for context and traditional
forms while incorporating modern requirements for flexibility
and spaciousness in interior layout and efficiency in overall
plan," observed a jury member.
ARCHITECTURAL DESIGN
Honorable
Mention
Loyola Jesuit Center, Portland, Ore.
Submitted by: Walsh Construction
Co.
Designers and builders of the Loyola Jesuit Center in East
Portland kept the center's surroundings in mind when planning
the four-building residence for Jesuit priests.
The center, located in a quiet, wooded neighborhood, features
two residence buildings, a chapel/meeting room and a building
that will serve as the regional provincial office for the
Jesuits. Western red cedar siding was used on all the exteriors
and is reflected in a water feature that wraps around the
chapel backdrop of fir trees and gardens through a window
wall in the chapel.
The design of the Loyola Jesuit Center is particularly suited
to the site and intent of the facility. With a moderate slope
and heavily wooded perimeter, the buildings are low, clad
in cedar and complemented by a standing seam metal roof. The
outdoors come inside with extensive interior paneling and
finish carpentry.
MECHANICAL PROJECT
Award
of Excellence
|
|
HRSG Erection Project
Photo courtesy of SP Newsprint
|
HRSG Erection Project, Newberg, Ore.
Submitted by: TIC - The Industrial
Company, Tualatin, Ore.
Despite completing a tough job made tougher by a complete
revision to the entire project schedule, the Heat Recovery
Steam Generator (HRSG) Erection Project's mechanical contractor,
TIC, was still able to complete the project ahead of schedule
- and without a lost time incident.
On paper, the HRSG Erection project looks routine. What
makes this erection project complicated is the small site
in which crews had to erect the mammoth components. Each HRSG
measures 123 ft long, 60 ft. tall and 11 ft. wide with a stack/silencer
that towers to 150 ft., while the construction site was just
150 ft. long and 250 ft. wide. The site included not only
the combustion turbine and HRSG, but also utility pipe racks,
motor control/electrical building and water treatment building.
"Unless you have been involved with one of these projects
you might not appreciate what was accomplished," noted
one juror.
Crews coined the phrase, "construction in a bottle"
to describe the project. Due to schedule constraints and material
deliveries, the project needed to be built from the outside
in. By the time TIC started construction, the utility pipe
racks, motor control/electrical building and water treatment
building had been completed and the combustion turbines had
already been set. The combination of the existing infrastructure
and a 115 kV power line provided for a very tight project
site. Surrounded on all four sides by existing structures
and structures under construction, access to install components
was extremely limited. Material staging areas were confined
to two locations remote from the construction site; the primary
staging area was approximately one half mile away.
|