Hoffman is in charge of building the Brightwater treatment plant. This year it plans to complete the buildings, backfill structures, build digesters, install mechanical and electrical systems (pumps, piping, ducts), and begin landscaping.

Project Name: Brightwater Treatment Plant
Main facility
Location: Bothell Wash.
Total Construction Cost: $73 million
Construction Start Date: 2007
Construction End Date: 2010
General Contractor: Hoffman Construction
Subcontractors: University Mechanical


Sign in to Comment
To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.