DBM Moves Bridge For Sound Transit
New bridge location will accommodate
Sound Transit's Sounder Trains.
Tacoma - DBM Contractors Inc. recently completed the erection
of a 120-ft. long, 260-ton steel girder bridge that completes
a section of the Sounder Train route for Sound Transit here.
The bridge erection and placement was part of a $9 million
contract to complete a crucial section of track for Sound
Transit.
To minimize the construction impacts on Portland Avenue,
one of Tacoma's busiest roads, DBM assembled the bridge on
a site adjacent to its final position.Once assembled, DBM
utilized a hydraulic skid system that DBM designed for moving
container cranes to launch the bridge over the roadway to
mobile cranes positioned to move the bridge for final placement.
The entire move was completed between 10 p.m. and 6 a.m. and
required the use of three mobile cranes to lift and set the
bridge in place.
DBM worked with general contractor Stacy and Witbeck, Inc.
of Portland, Ore. Fought & Company, Inc. of Tigard, Ore.,
fabricated the steel and the cranes were provided by Ness
Cranes of Seattle. The 1.27 miles of track were completed
on November 19th, 2003.
|