|
Northwest Renovations
Three buildings in the Portland-Metro area are getting upgrades designed to give them new functionality.
Soho 321, Portland
A former warehouse at Third and NW
Glisan in Portland’s Old Town District is
undergoing a transformation from storage
to office and retail space while keeping the
flavor of its century-old design.
Originally the Hunt Transfer Building,
the 89,000-sq-ft, seven-story warehouse was
used as a storage facility. The top floor of
the building was once used for automobile
storage. Cars were taken to the storage area
using a 20,000-lb freight elevator.
“It’s the largest working freight elevator
west of the Mississippi,” says Mick Gross,
vice president of construction for JBH Real
Estate. Gross adds that the existing elevator
will come out in pieces and be replaced by
three new elevators in the existing space.
Construction costs for renovation of the
building are approximately $25 million.
Design services were provided by EDA
Architecture & Planning of Portland.
The renovation began with a soft demolition
in July 2007. Structural demolition
began in early 2008.
Gross says occupancy for the first and
second floors is set for early this year, and
there are commitments for some of the
space on the third through seventh floors.
He estimates that the building was about
25% leased as of December.
Plans for the first two floors of the building
include a restaurant, coffee shop and
bakery in the lobby with a salon and spa
occupying much of the second floor. Floors
three through seven will be primarily office
space.
Gross says the building was constructed
on some reclaimed river bank, and timber
pilings were used on the east end of the
building to lock it into place. The renovation
required micropiles on the east end of
the building to meet current earthquake
standards.
“The amount of steel we put back into
the building was kind of unexpected,” he
says. “It’s probably stronger and more stable
than when it was built.”
Lead designer Louis Martinez, of EDA
Architecture & Planning says the building
had to be opened to “make it alive. It was a
big concrete box.” The renovation plans
called for the addition of several large windows
and additional daylighting in the
south elevation.
The building is aiming for LEED silver
certification. “A building like this was
perfect for LEED,” Martinez adds. He cites
the simplicity of the original design and the
large amount of concrete that could be
recycled as factors in achieving certification.
The building retains its historic flavor.
“We’ve kept almost every ornament, decoration,”
Gross says. “Anything that had
some period look to it, we’ve maintained.”
He adds that some of the original colors
and glazes, and some copper detailing on
the front of the building, would be restored
as part of the renovation.
Lincoln Hall, Portland State University, Portland
Lincoln Hall, Portland State University’s
oldest building, will be getting a thorough
facelift in the coming months.
“It’s just kind of sad and suffering,” says
Linda Wall, construction project manager
for PSU. “It was once a grand building.”
The building was originally constructed
in 1911 as Lincoln High School. It was the
first building occupied by PSU when the
university moved to the South Park Blocks
in 1953 and currently houses the university’s
fine and performing arts programs.
The building remodel is termed
“deferred maintenance” and includes new
mechanical, electrical and life-safety systems
as well as a new roof. The remodel will
also bring the building up to current seismic
code and accessibility standards.
Upgrades will be constructed with an eye
on LEED certification; Wall says LEED silver
is a certainty, and gold is a possibility.
Design services are being provided by
BOORA Architects of Portland. Howard S.
Wright Construction of Portland is providing
construction manager/general contractor
services.
Currently, the project is in the design
phase, and no subcontractors have been
selected. The building has been vacated and
is undergoing abatement with services provided
by Lake Oswego Insulation of Lake
Oswego, Ore. The construction costs are
estimated at approximately $20 million.
Michael Tingley, principal with BOORA,
says LEED gold is a possibility on the project.
“We think we’re close,” he adds. “There
are a series of things yet to be finalized in
the design.”
Initiatives that will contribute to the
LEED certification include a reflective roof,
a high level of construction waste recycling,
ecofriendly materials on the interior and
reusing as much of the existing material as
possible.
The renovation plans also call for significantly
more natural daylight, which will
contribute to LEED points. Tingley says
that the plans call for reclaiming skylights
that were originally in the building. “There
were light wells in the center of the building
that got filled in,” he says. “We’re reopening
them.”
Reopening the skylights will contribute
to reaching a goal of getting natural daylight
to 75% of the occupied space.
“As the building is almost 100 years old
and has been renovated many times, we
anticipate many unforeseen conditions”
when construction begins, Wall says.
Selected demolition will begin in March.
Structural system construction is scheduled
to begin in May with a goal of completion
by July 2010. The building will be ready for
occupancy by September 2010.
Vibra Specialty Hospital, Portland
Portland’s former Physician’s Hospital
has a renewed purpose with its new owner,
Vibra Healthcare.
The Pennsylvania company took over the
hospital facility in 2006 with the goal of
opening a long-term assisted care hospital.
The first phase was completed in May 2007
and the second phase was completed in late
2008.
The hospital received occupancy permits
for the most recent 17 beds on Dec. 23, and
that brings the total number of open beds
to 73, says Judy Ingala, the facility’s CEO.
Craig Shartner, operations manager with
Rehfeldt Construction of Vancouver, Wash.,
says that the renovation primarily involved
upgrading systems and facilities to bring
the building up to current standards and
codes for a medical facility. He says outdated
HVAC systems, medical gas piping, generators
and emergency electrical panels
were some of the systems and equipment
that had to be replaced.
Rehfeldt Construction served as general
contractor on the first phase of the project
and as the owner’s representative on a
design-build contract for the second phase
of the project.
Waterleaf Architecture of Portland provided
consulting services on the first phase
and design services on the second phase.
Construction costs to date total approximately
$8 million. Projected costs through
the end of all phases of the project will be
approximately $20 million.
Cherry City Electric of Salem, Ore.,
served as the electrical contractor; Alliance
Systems of Hillsboro, Ore., was the
mechanical contractor.
Renovation plans also called for some
updating of the facility, including remodeling
double-occupancy rooms into single
occupancy.
While the project did not aim for any
LEED certification, Rehfeldt Construction
did “recycle and reuse everything we
could,” Shartner says.
Rehfeldt recycled some of the HVAC
equipment. “We saved a couple million dollars
by refurbishing it,” says Trent Rehfeldt,
company president. The contractor also
worked with Energy Trust of Oregon on the
facility’s lighting plan.
Originally constructed as Woodland Park
Hospital in 1962, the building went
through a series of additions and renovations
before becoming Physician’s Hospital
in 2004. The original drawings were done
by hand, and Shartner says that many of
them had been changed and didn’t match
what crews found when they began renovations.
“We had a lot of unknowns,” he adds.
“We had tight timelines and had to keep
chasing things down to get everything
right.”
Shartner said that the first two phases
have completed renovations on approximately
half of the 160,000 sq ft in the building.
A third phase will be based on the
needs of the hospital.
King Street Station
Seattleites have no excuse to be late, now
that the clock tower on King Street station
in Seattle has been repaired. Modeled after
the campanile at St. Marks in Venice, the
tower is part of the train station that
anchors the lower part of downtown.
 |
Crews installed glass tiles on the roof of the clock tower at King Street Station. (Photo courtesy of city of
Seattle) |
The restoration is the second phase of
work now under way. Biwell
Construction, Bellevue, is in charge of the
project that calls for replacing the existing
roof, repairing lighting the four clock
towers.
The building has been though several
incarnations since it was designed by
Reed and Stern, the architects who created
Grand Central Terminal in New York City.
During World War II, King Street
Station was a major portal for servicemen
on their way home.
The Burlington Northern Railroad took
over the building and changed into office
space, covering the ceiling and a marble
staircase and balcony on the second floor.
Now the building is a critical transportation
hub, connecting commuter trains with
buses and serving long distance passengers
and freight trains.
The city of Seattle bought the building
from the state Department of
Transportation for $10 in early 2008, with
the intentions of returning the building to
its former glory. Total cost of the renovation
is expected to be about $30 million.
Fundraising is now taking place to
remove the false ceiling that will expose the
original terra cotta work and restore the
balcony and staircase.
Currently replacement of the station
roof, removal of the microwave dish, and
repairs to clock tower is being supervised
by Biwell. Anticipated substantial completion
of work is early 2009.
Restoration of King Street Station will
be funded by contributions from the city,
the state and the federal government. The
voter-approved Bridging the Gap levy will
provide $10 million and the Washington
State Department of Transportation
(WSDOT) will contribute $16.5 million in
local, state and federal funds.
Currently only the first floor of the
building is being used. The city of Seattle
may restore the second and third floors
eventually, and lease the space, says Josh
Stepherson, public information officer
with the Seattle Department of
Transportation. Burlington Northern used
the space for storage.
|