|
After Removing Tons of Soil, Brownfield site Fit for Housing
For 14 months, Brenda Corbett watched a wave of long-awaited
change rolling over her neighborhood in west central Spokane.
On the edge of the neighborhood, 78 acres in the Spokane's
downtown sat empty and neglected for more than 50 years. The
property was drawing more crime than development. It was a
dumping ground for refuse. The land was riddled with contamination
from years of use as a rail maintenance yard.
A Couer d'Alene, Idaho, developer in just more than a year
cleaned up this massive site, removing 223,000 tons of contaminated
soil. That's enough polluted soil to cover 83 football fields.
The developer's plans call for building 2,600 residences and
1 million sq.ft. of commercial space on the land, transforming
the new development into a hub of activity.
For Corbett, the benefits are much simpler. It's a chance
for the neighborhood to become whole again. "What we're
gaining is a catalyst for change," said Corbett, who's
lived there 35 years. "We have a promise of new neighbors."
Developer Marshall Chesrown of River Front Properties is making
that promise to be a good neighbor to this Spokane neighborhood
in the heart of the city's downtown and along a portion of
the Spokane River. About $5.6 million was spent this past
year cleaning up the contaminated property, now called Kendall
Yards. The site received a $3.4 million loan from the state's
brownfields loan fund, the largest such loan in the nation.
In April, the EPA awarded the project team a National Notable
Achievement Award for its approach in getting the site assessed
and cleaned up in 12 months, a process that normally takes
about two years.
Kendall Yards, formerly known as the Summit Property, was
operated by Union Pacific Railroad from 1914 to 1955. Once
a railway maintenance complex, the land stretches about 30
city blocks. Because of the property's former use and some
earlier testing by a previous property owner, it was no secret
the land was contaminated. Officials estimated about 90,000
tons of soil would have to be removed from the site. In the
end, that number would nearly triple.
"We found a lot of stuff that wasn't on the record,"
said John Foxwell of Geo Engineers, the Portland-based environmental
consulting company working with Chesrown.
The bulk of the contamination was limited to about 20 acres,
said Sandra Treccani, site manager for DOE. While no ground
water contamination was found, officials found fly ash with
lead and arsenic. The fly ash was from coal-fired locomotives
that once were worked on at the site. There were many areas
where the ash had been mixed in with the soil, Treccani said.
|
Also found was bunker C, a grade of
petroleum-based fuel that's very thick and once was used to
fuel old train engines. While the bunker C also was no surprise,
officials were shocked to learn it had moved much deeper than
thought the thick fuel could travel - in some places as much
as 60 to 70 feet below the final grade, Treccani said.
Both Treccani and Foxwell point to the massiveness of the
project as a hurdle in its cleanup. Most of the projects she's
worked on in the past required the removal of about 20,000
tons of soil, Treccani said. This site was 10 times the size
of any she had ever managed.
"It had been sitting there for a long, long time and
nobody wanted to tackle it," she said.
Kendall Yards also was one of the biggest challenges Geo Engineers
has faced, Foxwell added. "It's a daunting project, there's
no doubt about it," he said. Its enormity and complexity
is why the previous property owner did not follow through
on cleanup plans, he added.
Typically, cleanup projects like Kendall Yards take many years
to complete, Foxwell said. Although nearly triple the contamination
was found, the project was completed only 30 days past its
original finish date, he said. Envirocon, the contractor,
did a fantastic job of moving the soil, Foxwell said.
He's never worked on a project where the developer, the regulatory
agencies and the financier were more committed to a common
goal, Foxwell said. Everyone had a vision and understood the
importance of this project to the local economy, he said.
"They rose to the challenge and saw the benefit to themselves
and the community," Foxwell said.
Chesrown could have excavated the site 15 feet and capped
the remaining contamination with concrete. However, he chose
to remove it all because he wanted unrestrictive use of the
property. In some areas, especially in the case of the bunker
C, Chesrown went three to four times deeper than required,
Treccani said. This choice doubled the cost of the cleanup,
she said.
However, Chesrown was undaunted by this. "We think it's
the absolute best move for Spokane," said Chesrown, who'd
never worked on a brownfield site before Kendall Yards.
Chesrown's plans for the site will be finalized when a new
planned unit development is approved by the city of Spokane.
Preliminary plans (www.kendall- yards.com) call for building
a combination of townhouses, apartments and condos along with
shopping plazas and retail space. The urban development would
be directly connected to downtown Spokane. More people are
eager to make downtown areas their homes, said Chesrown, pointing
to such examples as Seattle, Portland and Boise, Idaho. The
first phase of construction, to be from Monroe to Maple streets,
should take about 18 months to complete at a cost of about
$300 million, Chesrown said.
The project is expected to have a major impact on Spokane's
downtown, as well as throughout the city. An estimated 500
jobs will be created during the construction phase. Up to
2,500 permanent jobs could be created when the commercial
space is finished, according to statistics from the Washington
State Department of Community, Trade and Economic Development
(CTED). The redevelopment will return more than $32 million
to the state and local government during construction, according
to CTED.
Located in one of the poorest areas in Spokane County, the
development's economic impact will come in many ways. This
project will increase property values, provide valuable jobs
and, with the city's Centennial Trail running through it,
serve as a gateway to the surrounding community.
Perhaps more important, downtown Spokane is getting a neighborhood
that's now safer for families, Foxwell said. "Before
the first yard of cement concrete is poured, the surrounding
neighborhoods have received a tremendous benefit," he
said.
Jill FitzSimmons is a freelance journalist working with the
Washington state Department of Community, Trade and Economic
Development.
|