|
From Condos to Assisted Living
Housing Leads Seattle Projects
The gardentop roof the the Washington
Mutual Tower is a highlight of the building.
The busy pictures in a Where is Waldo book inspired one Seattle
developer to hide a replica of the skinny, striped-shirted
guy in its architectural model of the South Lake Union area.
Even adults, looking at Vulcan's model depicting its projects
couldn't find Waldo.
With 25 projects under way in the downtown core, developers
could easily hide several Waldos between Lake Union and Quest
Field. Vulcan alone announced that it would soon start five
projects near Lake Union. The Downtown Seattle Association
reports six others owned by different developers in the planning
phase.
Most of the projects involve some sort of housing - hotels,
apartments, assisted living, or condominiums. Laboratory and
research space along with Group Health Cooperative headquarters
are planned for the Lake Union area.
The biggest project under construction in downtown is the
The Washington Mutual Tower/ Seattle Art Museum addition,
valued at $300 million.
If all the projects start before the end of the year, contractors
will be looking for more than Waldo. They'll need a guaranteed
supply of skilled craftsmen and the reassurance that subcontractors
haven't over extended themselves financially.
"We aren't having labor problems yet, but as the bigger
projects come on line, somebody's going to," said Kevin
McCain, project manager with Skanska USA Building, Seattle.
Sheraton Hotel
Crews from Skanska USA Building, Seattle, plan an extended
stay at the downtown Seattle Sheraton as they build a 25-story,
$96 million addition, under a guaranteed maximum price contract.
The first phase of construction is the most critical - the
three story tie-in to the existing podium level and a complete
remodel of all the services there, including ballrooms and
convention space.
"That's the most difficult part right now, because it
has to be completed before July 7, 2006 in order to accommodate
summer conventions," said Kevin McCain, Skanska project
manager. Work on that portion of the project started January
17, 2006. Not only does the renovation have to be completed;
the new podium level has to be done, as it provides exits
needed to obtain the occupancy permit.
McCain, who has three similar hotel projects under his belt,
sees the initial scheduling as the biggest difficulty of the
project.
Like other contractors around the Seattle area though, he
sees a potential labor problem as well. "We haven't had
any trouble so far, but once the other big projects come on
line, there could be one. Even if we don't have any trouble,
down the line somebody will."
Contractors like to brag about tight sites, especially in
urban areas, but this site makes a full sardine can look spacious.
The back of the building is next to I-5, the south side next
to a freeway entrance ramp, and the west and north sides are
major retails streets. "We are on just in time delivery
for everything. We are even having trouble with some of the
formwork because there is no place to store anything,"
McCain said.
One thing all hotel guests want is a restful stay, so the
demolition work on the job has also been difficult. "I
know the hotel is getting its share of complaints, but sometime
we just have to get the work done. We are working closely
with the hotel operations staff to make sure we cause as little
disruption as possible," McCain said.
When completed, that area will look more modern, but the
design finishes will still echo the existing building. The
new podium level will include restaurants and other services.
Skanska will also be extending the existing podium level,
and McDonald-Miller Facility Solutions, Seattle will take
care of the mechanical tie-ins and other mechanical work.
The poduim level in both buildings is steel frame. The new
tower is post-tensioned concrete.
Project Team
Owner: Sheraton Hotels
Architect: Callison, Seattle
General Contractor: Skanska USA Building, Seattle
Mechanical Contractor: McDonald-Miller Facility Solutions,
Seattle
Addition
Looking at the new WAMU tower design and construction, it's
harder to tell who had to be more creative - the designers
and contractors working on the building or the artists who
created the pieces that will eventually be housed there.
The need to be creative started at the inception of the project,
which started with a partnership between the art museum and
the banking company. Washington Mutual wanted to buy the parcel
next to the art museum so it could build a new headquarters
and put all its offices in one location. The Seattle Art Museum
didn't want to give up the land. It planned to build an addition
to its facility someday so it could have more exhibit space.
Matt Griffin, a principal with Seneca Group came up with
the daring plan to build both.
As it stands, the art museum will own the first four floors
of the tower. Washington Mutual and various other tenants
will lease the rest of the building from the art museum. After
10 years, the art museum can take those floors back from WAMU,
two floors at a time.
"At first everybody balked at the idea," Griffin
said. "How to design a building that could address the
needs of both parties was the major issue."
But, both saw the advantages. It allows more time for the
museum to fundraise to improve its collection. Washington
Mutual can build an urban campus in the downtown core. Creative
consultants and contractors solved the design issues.
Consider the flexibility needed to build one facility that
will be used for both a museum and an office building. The
list of juxtaposed needs seems endless. Totally different
mechanical and electrical systems are required to meet the
different uses, yet the building had to accommodate both.
Structural column placement could not be repeated throughout
the building, as would occur in a normal office space. Instead
the column placement had to be flexible between some floors
to allow the art museum more available space for exhibits.
Electrical needs in the museum are less than those in an
office. Humidity control is a critical part of preserving
art work, but not all that important in an office. Probably
the only thing easy about the project is that the museum will
close for one year to allow for all the tie-ins to the new
space and demolition of the part of the existing structure.
David Yuan, a principal architect with NBBJ summed up the
problem. "You have to mush two buildings together that
will eventually morph over time. It's almost like Siamese
twins." NBBJ, the architect of the building has spent
about 51,000 hours to date designing the SAM WM project. This
is equivalent to a single person working 40 hours per week
for about 25 years.
As the contractor, Sellen Construction's project management
skills had to be flawless and communication between the two
owners: Washington Mutual and the Seattle Art Museum; the
two architects; NBBJ for the office tower and LMN for the
art museum and has to be extraordinary. Double that skill
level for the primary subcontractors on the project, since
they have to work under Sellen, but are design build subs
under the architects.
As one of the first architects in Seattle to use a computer-based
communication system for project management, NBBJ took the
lead. Through a central database, all the major parties have
instant access to the same documents. "They were pretty
rigorous about establishing protocol," said Adam Kriefall,
project manager with Sellen Construction, Seattle.
Meeting all the deadlines for permitting was another difficult
goal, because the building has two uses and has to meet two
sets of building codes. "We went through many, many sessions
with the project teams, and that kind of thing will never
be replaced by technology," Yuan said.
Sellen was a major part of the team from the very beginning,
especially during the costing process.
With two owners but overlapping systems on every floor, tracking
costs and administering the project is also complicated, down
to the littlest detail. For example, the museum is tax exempt,
but the bank tower is not.
"I really appreciate the scope. This is the longest
and most expensive project I've ever done," Kriefall
said. "Teamwork is the most important part of the project,
because no one person knows everything and nobody knows the
complete answer to any question."
Horizon House
Most of the housing under construction in downtown Seattle
is geared toward empty nesters or young single professionals.
Horizon House, located across the street from Virginia Mason
Hospital, is attracting people from the higher reaches of
the age spectrum.
The assisted living facility for seniors already has a waiting
list, even though the foundation is still under construction.
Lease Crutcher Lewis is the general contractor on the $50
million project, which will provide 100 independent living
apartments and 52 assisted living units. With views of Puget
Sound, an indoor swimming pool and its location close to most
of the hospitals in Seattle, the facility was bound for success.
Next door is the original Horizon House, also a senior-only
apartment building.
The building is made of a mix of concrete applications, including
precast and post tensioned. On the interior, the owner is
trying to be as accommodating as possible to future tenants.
"We can't move around major components like plumbing,
but we can change things like finishes," said Larry Bjork,
project manager with Lease.
Individuality is key throughout the project with 11 different
apartment configurations available.
"Our biggest concern is meeting the needs of all the
tenants as they come in and want to customize their apartments.
Lease has designated specific people to help with that,"
Bjork said. "Even in the planning stages, residents knew
what they wanted."
To keep ahead of individual demands, Lease created a set
of deadlines for the residents, organized by floor. "After
that it's just a matter of managing the information,"
Bjork said.
The contract is a guaranteed maximum price contract.
Project Team
Owner: Horizon House, Seattle
Architect: NBBJ
Developer: Seneca Real Estate Group
Contractor: Skanska USA Building, Seattle
Mechanical: University Mechnical
Electrical: Sasco Electric
Alley 24, just being completed, will be the new home of NBBJ
and Skanska USA Building.
Vulcan Real Estate
Vulcan is expecting a stellar year in 2006 and plans to start
construction on five different projects as part of the company's
goal to rehabilitate the South Lake Union neighborhood.
The redevelopment project is one of the largest such efforts
in the United States and will consist of more than 10 million
square feet when completed.
2005 highlights for the company include:
- 900,000 square feet currently under construction worth
$300 million.
- Three million square feet in the development pipeline.
- Leased approximately 300,000 square feet including 182,000
square feet to Group Health Cooperative and 53,000 square
feet to Cole & Weber/Red Cell.
- Pre-sold 259 condominiums at a total value of $138.5
million.
- Announced three new mixed-use residential projects totaling
672,599 square feet.
- Secured permitting for Phase II of UW Medicine Lake Union,
which will total 284,000 square feet. Construction for Phase
II is scheduled to begin in 2006.
"There is a huge push for these types of projects in
the marketplace," said Ada M. Healy, vice president of
Vulcan Real Estate.
|