|
Updated Library Design Stresses Neighborhood
Themes
Materials Prices Boost Bid Results
By Lia Steakley
The library boom continues in Seattle. A year after the city's
award-winning Central Library opened, 15 library branches
have been completed, five more are under construction and
another seven will be finished by 2007.
The citywide overhaul includes constructing new branches
in burgeoning neighborhoods, replacing aging structures and
renovating and expanding branches.
Seattle's "Libraries For All" building program
price tag is an estimated $280 million, which includes design,
construction, and furnishing costs for all 27 branches and
the new 362,987-sq.-ft. Central Library. Voters bankrolled
the majority of the ambitious capital plan in 1998 when they
approved a $196.4 million bond measure and the Seattle Public
Library raised an additional $82 million in private funds
to complete the projects. At the time, the bond was the largest
library improvement measure passed in the nation's history,
said Alex Harris, Seattle Public Library capital program director.
Seattle library trustees chose branch designs incorporating
green building practices. "We want these buildings to
last," said Frank Coulter, Seattle Public Library program
manager. "We don't want the branches to look old in 20
years so we chose a lot of materials for the long term."
Architects and construction firms varied for each project
to ensure the branches were unique and reflective of the neighborhoods
they served. The result was 27 branches influenced by the
residents who frequent them.
But some of the more unusual design aspects had contractors
scratching their heads.
For example the expanded 13,500-sq.-ft. Greenwood Branch
opened in January with front-door seating fashioned from massive
Montana boulders and a patterned floor concealing a radiant
heat system, both of which proved to be quite a job for Seattle-based
W.G. Clark Construction Co.
Seattle architecture firm Buffalo Design chose a random pattern
with portions of carpet, vinyl and integrally colored concrete
material for the $4.9 million building's floor. "The
contractors were trying to pour concrete and also trying to
strike these pattern lines in the concrete," Coulter
said.
Under part of the floor is a radiant heat system. "It
was a complicated floor structure," said Howie Kellogg,
a project manager with W.G. Clark. "We've probably done
three slabs like that out of hundreds of projects."
The tricky part came before the roof was fastened and Seattle
rain posed the threat of water becoming trapped in the system.
The complex slab design meant the building wasn't really watertight,
so W.G. Clark used electrical conduit sleeves as weep holes
to drain the water trapped in the sandwich slab.
Once contractors conquered the floor design, the next challenge
was the $7 million building's front entrance. A 30-ft.-tall
aluminum and glass curtain drops from the roof around the
front door, wrapping around massive boulders that provide
decoration and seating.
The hole left for the rocks, which are stacked in layers
similar to a wedding cake, was 3 ft. tall and 16 ft. long.
Again, sealing the design from rain elements was a problem.
"We were concerned because the rock penetrated the exterior
glass curtain wall," Kellogg said. "Concealing all
the joints from the rock so the water didn't migrate from
the outside was a problem."
Eventually, W.G. Clark found a solution but Kellogg admitted
that he "spent a lot of time fussing and figuring it
out." In the end, a short concrete wall was poured to
waterproof the base of the stacked boulders and then custom
fabricated sheet metal was installed to seal areas between
the upper boulder and the aluminum curtain wall. All of the
joints were then sealed extensively with caulk, said Kellogg.
About 8 mi. south of the Greenwood library is the new $5.4
million Beacon Hill branch, which was designed by Carlson
Architects of Seattle and opened last summer. Built by Steele
Corp. of Edmonds, Wash., the 10,800-sq.-ft. building has sweeping
roof forms to allow natural light, a large canopied stone
entry plaza and garden areas.
"The roof of the library is composed of two overlapping
curved forms that are linked by a clerestory window. The curve
of the roof is formed by lapped panels that create facets
on the metal roof," said David Kunselman, Seattle Public
Library project manager.
The unusual roof required the contractor to work with a steel
fabricator to produce one piece of steel with compound curves
going in two directions. The roof creates a pavilion that
floats above glass walls. The walls are interrupted by rooms
that are playfully, arranged like slate clad boxes that pass
through the glass.
Similar to the Greenwood site, the Beacon Hill branch's floor
also required creativity. The floor was raised 18 in. to provide
flexibility for future configurations of the library floor,
space for cabling and room for circulating air. Concrete panels
were put down and then covered with carpet squares, allowing
library staff to pull up the panels and reconfigure the floor
outlets.
But the design couldn't bear the weight of heavy machinery,
so some jobs such as interior painting and installation of
light fixtures had to be completed before the floor was installed,
Kunselman said.
Kunselman is currently overseeing construction on the new
Northgate branch, which is slated to be completed in June
and was designed by Seattle's Miller/Hull Partnership. The
more than $8 million project includes a 10,000-sq.-ft. library,
20,000-sq.-ft. community center and 1.67-acre park between
the two buildings.
Absher Construction Co. of Puyallup broke ground on the branch
this spring, which was later than originally scheduled because
of project costs increases. The first bids were over budget
and so the library board reworked the project's scope and
secured additional funding to avoid reducing the branch's
size.
The Northgate branch was one of three projects that have
been rebid because of escalating material costs. Other branches
with bids beyond budget were the new Montlake branch, which
was more than $500,000 over; and the Southwest branch expansion
project that came in $1.26 million over budget. The Douglass-Truth
Branch, was about $800,000 over budget but the library board
decided to increase its budget rather than rebid the project.
A unique aspect of the Northgate library's design is a large
storm water vault below the park. Storm water from the property
will be collected, filtered and stored in the underground
chamber to be used to irrigate the property. None of the other
branches, and few buildings in the city, has such a storm
water system.
Another sustainable building feature is that 90 percent of
the material from the buildings demolished at the Northgate
site will be recycled or reused. "The challenge for the
contractor is to demolish these buildings, sort them and make
sure they are not going into the waste stream but are being
used onsite or will be recycled," Kunselman said.
The asphalt will be ground and placed underneath the future
asphalt, and the former concrete footings will also be crushed
and used as fill below future footings.
Next for the city is a new 5,000-sq.-ft. South Park branch
designed by Johnston Architects of Seattle and scheduled for
completion next year. The $2.7 million building will have
a collection capacity of 18,700 books and materials, a special
area for children, computer workstations and instructional
spaces. The new library is paid for through a $6 million Opportunity
Fund, which was part of the 1998 bond and pays for unanticipated
neighborhood library capital needs for underserved areas of
Seattle.
|