|
Link Light Rail Tops the List for Budget,
Complexity and Ambition
Transportation is always an issue in Washington State, whether
people are talking about congestion, funding or technical
problems. This year various agencies have experienced all
three.
Easily
one of the most wide ranging transportation projects in the
nation, Seattle's central link light rail is well under way
with five major contracts running simultaneously.
With four of the five major contracts coming in at six percent
under the estimate, Sound Transit project managers are hoping
to pull off an economic and engineering triumph at the same
time. Construction cost of this phase of the project is estimated
at about $1.1 billion, but unless problems develop, costs
should be considerably lower.
The most technically difficult part of Sound Transit's endeavor
is boring the elevator access that will carry passengers down
to the station under Beacon Hill and a 4,300 foot tunnel that
connects the Rainier Valley and the industrial area just south
of downtown Seattle. Difficult soil conditions include groundwater
and three-foot deep pockets of sand.
Right now prime contractor Obiyashi is digging 160-ft. deep
elevator shafts that will eventually bring passengers down
to the rail station. To deal with the unstable soils, Obiyashi
is using a slurry wall to support the perimeter of the shafts.
Then it will inject concrete into the wall, displacing the
slurry.
When tunnel boring starts this summer, it will be the deepest
ever attempted in glacial till in North America, according
to Sound Transit. Obiyashi will be using SEM, or "sequential
excavation mining technique". Displacing small amounts
of earth at a time will help control the excavation, and also
possible disruption of the urbanized area on the surface.
Crews are now using the cut and cover method elsewhere on
Beacon Hill to create the space for the tunnel-boring machine
to enter. Due to arrive in June, it is being built in Japan
by Mitsubishi Heavy Industries. Ltd.
Continuing on the route south, riders will travel through
Seattle's Rainier Valley, one of the most economically depressed
areas of the city. There RCI Herzog is working on relocating
utilities, burying them underground and building the track
down the center of the street. "As far as community impact
goes, this is the most challenging part of the project,"
said Geoff Patrick, Sound Transit, media spokesperson. Local
merchants have long voiced resentment about the project; fearing
traffic congestion will deter customers and force businesses
to relocate. Traffic and utility shutoffs are also affecting
local residents.
The final phase of the central link was recently awarded
to PCL Construction Services Inc., which will build a five-mile
elevated track from the Rainier Valley to Tukwila. The contract
also includes an option to continue the track 1.4 miles to
Sea-Tac International Airport.
Beatty Balfour is charge of what is probably the biggest
remodel in Seattle as it upgrades the existing bus tunnel
for light rail use. A stub tunnel, which will provide a place
for the trains to turn around is the first order of business
and is now under construction at 8th and Pine. Work calls
for upgrading the electrical and mechanical systems, improving
fire safety and installing a communication and signaling system.
While excavating for a bridge that will run over the Duwamish
River as part of the project, contractors ran into an archeological
site. It is now being investigated, with the remnants preserved.
"We expect to be finished well before it has an impact
on the construction schedule," Patrick said.
Modern Needs Meet Antiquity, Again
Sound Transit wasn't the only agency to run into an ancient
Native American Village, during construction. Washington State's
effort to build bridges for the future is also digging up
the past.
State transportation officials were surprised to find hundreds
of burial remains and artifacts while constructing a graving
dock near Port Angeles, Wash. for the repairs on the east
half of the Hood Canal Bridge. A similar find is expected
if work proceeds on replacing the Evergreen Point Floating
Bridge, which crosses Lake Washington between Seattle and
Bellevue.
"Nobody knew the significance of what we going to find
(at the graving dock site), not even the tribe," said
Linda Mullen, spokeswoman for the Washington State Department
of Transportation.
Fifteen months and $58 million into the project, work halted
at the graving dock location last December. In February, a
six-member expert panel reviewed three options for moving
the project forward:
Locate a new graving dock site and either renegotiate the
current general contracting agreement
Rebid the pontoon and anchor construction portion of the
contract
Find a new general contractor and leave the process of selecting
a new site in the firm's hand.
In an effort to curb costs and meet a 2008 deadline, WSDOT
is simultaneously working on the first two suggestions. Eric
Soderquist, project director for the Hood Canal Bridge team,
says, "The goal right now is to concurrently begin negotiations
with the contractor first to build anchors, to prepare for
negotiations on the overall re-pricing of the contract and
begin work on new contract documents in case any portion of
the negotiations fail."
Transportation officials are studying three potential dry
dock sites -Mats Mats Bay north of Port Hadlock, Port of Everett
South Terminal and a combination of existing Puget Sound dry
dock facilities proposed by FCB Facilities Team-until mid-summer
when a final location will be chosen. Work has also begun
on developing new graving dock concepts at the Port Ludlow
Quarry and the Port of Everett and refining concepts for building
pontoons at existing facilities in Tacoma and Seattle.
Talks with project general contractor Kiewit-General, a Port
Angeles, Wash.-based joint venture of Kiewit Pacific Co. and
General Construction Co., began in mid-April.
In light of the $238 million Hood Canal projects archeological
finds, the Duwamish Tribe is wondering what will happen when
construction begins on one of the nation's oldest floating
bridges, State Route 520.
The state has yet to finish a draft environmental impact
statement, but talks with the tribe about potential sacred
land are already underway. Design options under consideration
include a 4-lane or 6-lane bridge to replace the current six-mile
span, which opened in 1963. The 4-lane option would cost from
$1.7 to $2 billion and adding two additional lanes would up
the price to between $2.6 and $2.9 billion. Construction is
expected to be completed by 2020. The final environmental
impact statement will be finished near the end of 2005 and
construction is expected to begin in 2009.
Monorail Project Faces Legal, Funding
Challenges
After months of negotiations, the Seattle Monorail Project
board has yet to sign an agreement for the construction of
the city's 14-mile Green Line. But despite whispers about
the project's sole bidder being $200 million over costs, monorail
officials say negotiations with Cascadia Monorail, a 29-company
consortium headed by Washington Group International, Fluor
and Hitachi, will continue until an agreement is reached.
"We'll
negotiate as long as it takes," says Natasha Jones, spokeswoman
for the Seattle Monorail Project. As of mid-April, no agreement
had been signed.
A previous project timeline set the end of 2004 as the deadline
for an agreement to be signed, with construction to begin
this year and the railway system to be operations in 2009.
Jones and Cascadia representatives are tight-lipped about
the project being over bid and which portions of the design
are adding up to more than the $1.5 billion budget approved
by voters.
In the absence of a construction contract, a previous bidder
is tempting Seattleites with a sleek, relatively unobtrusive
model with a $1.35 billion price tag. Team Monorail, a 19-member
team led by Bombardier Transit Corp. withdrew its bid last
fall over the monorail board's tough liability standards and
is now asking for a do-over.
"We are suggesting that (Seattle Monorail Project) re-visit
the current procurement, reissue or modify the (request for
proposal) with the changes we are suggesting, and invite Cascadia
and Team Monorail to submit proposals," wrote Denis Bouvette,
vice president, Total Transit Systems Division, Bombardier
in a Jan. 14 letter to the monorail board.
But the monorail board shrugged off Team Monorail's request
and instead is moving forward with considering revenue-generating
options such as tourist and celebration trains. The specialty
trains would be available in off-peak commuting hours for
a premium price.
Tourists now spend about $13 for a view from the top at the
Space Needle and from $17 to $32 to board a harbor cruise.
The board is hoping to lure visitors to the new rail system
by promising a comfy ride and 360-degree views.
The trains may feature flat-screen televisions, movies, speakers,
restrooms and chairs that face the windows and could help
the monorail break even by 2020 without tax subsidies. While
the tourist trains would run between peak commuting times,
the celebration trains would be rented out for blocks of time
to host birthdays, wedding receptions or other parties.
While monorail officials and Cascadia continue negotiations,
the state Legislature is contemplating a solution to the project's
financial woes. Washington lawmakers are considering a bill
that would allow the Seattle Monorail Project to sell bonds
that last 40 years or longer if the Internal Revenue Service
permits. When voters approved the line in 2002, original finance
plans called for 30-year bonds. Construction is paid for with
a car-tab tax of $140 per $10,000 of vehicle value.
|