|
Artful Construction
Museum Projects are Unique Tasks
for Local Designers and Contractors
By Kathy Leotta and John Wolcott
|
|
|
Howard S. Wright
Seattle, is pouring the walls and foundation at the
National Flight Interpretive Center in Evertt.
(Photo courtesy of Howard S. Wright)
|
Museums have heavily traveled spaces that inspire and educate,
and they also must protect their sensitive artifacts.
That dual responsibility makes the task of creating museums
a tough one for designers and contractors.
"Unlike most other buildings, museums contain artifacts
that are sensitive to light, temperature and humidity,"
said Chris Linn, an associate principal at BOORA Architects
Inc. in Portland. "So they bring with them very specific
requirements, such as avoiding temperature and humidity fluctuations."
Museums also attract many visitors, which means flooring
and other materials have to be durable, but they also need
to be humane. "I look for materials that are warm, have
depth and variation."
Linn frequently specifies end-grain wood flooring in museums.
According to Linn, Oregon Lumber Co. is one of the leading
manufacturers of end-grain wood flooring in the United States.
"It is essentially wood blocks that have the grain oriented
vertically, so that you see the ends of the grain when looking
at the floor," Museums also require extraordinarily flexible
designs. The lights and walls in galleries, for instance,
have to be easily transformed to support a museum's frequent
change in exhibits.
Northwest Firms Involved Nationally
Northwest designers are familiar with the inherent complexities
in designing museums. BOORA Architects Inc. for example, served
as the design consultant for the Underground Railroad Freedom
Center in Cincinnati.
|
|
|
The barn at the
Underground Railroad Freedom Center in Cincinnati comes
from Kentucky and was reconstructed on site. Inside
is a pen where slaves were kept prior to sale.
(Photo courtesy of BOORA)
|
Like many other museum projects, the Freedom Center job included
a passionately interested group of constituents who sometimes
had divergent ideas. "The key is listening and being
respectful," Linn said. "But the best thing of all
is to have a great idea, present it well and have some conviction
about it."
Jones & Jones in Seattle is another Northwest firm that
has helped design a national museum. It served as one of the
project architects for the Smithsonian's National Museum of
the American Indian in Washington, D.C.
The designers incorporated suggestions from Native Americans
throughout North, Central and South America, and Jones &
Jones' own Johnpaul Jones, who is of Cherokee/Choctaw heritage,
was one of the designers.
Closer to home, three art museum projects are presenting
designers and contractors with unique design and construction
dilemmas.
Seattle Art Museum Partners with Washington
Mutual
The Seattle Art Museum (SAM) is expanding in a big way, tripling
its available space and accomplishing it decades sooner than
anyone anticipated.
When SAM built its original museum in 1991, it also purchased
a gutted brick building on the same block, anticipating future
expansion needs. "The original plan was to build a stand-alone
museum in that space, but it would've taken the museum 20
to 30 years to afford it," said Cara Egan, SAM's manager
of communications.
Then along came Washington Mutual, which was looking for
property in downtown Seattle for a new office building. Washington
Mutual approached SAM about a joint development on SAM's vacant
site. "It was an opportunity to expand the museum earlier
than we anticipated, and we figured out that the gradual expansion
of the museum could work," Egan added.
Washington Mutual purchased the downtown parcel and a nearby
garage from SAM and the Museum Development Authority (MDA)
for $27.7 million, which went toward SAM's capital costs on
the project. The total cost of the museum expansion and increased
endowment comes to $86 million.
The new development will consist of two separate buildings
- a 16-story museum building on First Avenue and a 42-story
Washington Mutual tower behind it on Second Avenue. Twelve
floors of the museum building will provide expansion space
for the museum, while the top four floors will provide additional
permanent office space for Washington Mutual.
SAM will initially occupy the lower four levels when the
museum expansion is completed in early 2007 and lease eight
floors to Washington Mutual until the museum needs the additional
space.
"The challenging part is creating a space that can serve
as both a museum space in the future and bank space in the
near term," said Scott Redman, executive vice president
of Sellen Construction Co. out of Seattle, the general contractor
on the project. "How do you make it work as a bank space
on day one, but ultimately it has to have all the more complex
mechanical and climate control, security and fire protection
systems that you'd typically see in a museum."
Part of the solution has been designing one building that
can serve both uses. For instance, in some areas the floor
loading capacity accommodates the museum's future needs although
it exceeds the capacity required by the bank in the near-term.
Some floor areas that the bank will occupy in the near-term
will later be removed to create two-story museum gallery spaces.
Similarly, the designers have found creative solutions for
the building's mechanical and electrical systems, such as
incorporating extra space to accommodate the museum's more
robust mechanical requirements.
"The team has done a great job of creating spaces that
can work for both owners," said Redman. "And they've
done so in a way that minimizes the cost to transition the
space from the bank's use to the museum's use in the future."
Construction on the museum expansion began in February, 2004.
The general contractor expects to place columns and beams
as quickly as two floors per week.
Portland Art Museum
The Portland Art Museum also strives to create special spaces
for its patrons and is creating a new one through the renovation
and restoration of a historic building. The museum's North
Building, which was acquired by the museum in 1991, was formerly
a Masonic Temple originally built in 1925. The cost of renovating
the North Building is estimated at $31.5 million.
|
|
|
The Portland Art
Museum is primarily a renovation project with Hoffman
Construction as the general contractor.
|
The building will include entirely new mechanical and electrical
systems. "We're taking a building heated previously by
hot water and introducing new heating and cooling systems,
all new electrical switch gears, all new lighting and all
new fire alarm and safety features," said Eric H.I. Hoffman,
operations manager at Hoffman Construction Co., the general
contractor on the project.
The North Building consists of the center section, the north
wing and the south wing.
"The center section, which will include a renovated
ballroom and library, is pure restoration," said Hoffman.
"The building's original finishes, which are much more
ornate than typically seen today, were all done with plaster.
So we've had to find capable craftspeople to match those older
styles of construction."
The south wing is being converted to new gallery space,
while the north wing will provide administrative offices.
Historic renovations on these two sections include removing
all floors and room structures while maintaining the sides
of the building.
The building renovation will include one additional floor
in both wings, as well as a new basement in the south wing.
"The kicker on the south is not only saving the exterior
walls," said Hoffman, "but building the basement
underneath."
According to Adam Bonner, Project Superintendent at Hoffman
Construction Co., this effort required two significant shoring
efforts.
First the contractor shored the building to allow for excavation
of the new basement. The basement was shored through an engineered
shoring system with a series of soldier piles and tiebacks.
Once the lagging reached the lowest elevation, the contractor
poured new footings, tied rebar in front of the lagging, and
shot a thick shotcrete retaining wall.
A second shoring effort was required to support the exterior
walls until the new structure was installed. "This was
the most technically challenging part of the entire project,"
said Bonner.
First the contractors cut a slot around the perimeter of
all floors and placed new shotcrete walls through this slot.
The team then removed the floor slabs but retained the existing
steel beams that supported the old floors. The concrete was
stripped off of the existing steel beams and every other beam
was removed.
The contractor then installed new beams by grinding down
the existing beam connection points and installing new beams
in these locations. The old beams that had not yet been replaced
were then removed and replaced with new beams in the same
manner.
These shoring efforts required extraordinary care by the
entire team to ensure that the building did not collapse.
"All demolition workers, concrete workers, and structural
steel workers had to be crystal clear on each step to make
sure the building stability was not compromised," said
Bonner.
Construction began in February 2004 and should be complete
at the end of the summer. Key subcontractors on the project
include Degenkolb Engineers, Elder Demolition, Northwest Cascade,
Fabrication Products Inc, R2M2 Rebar & Stressing, Inc.,
and Johnson Western Gunite Company.
National Flight Intrepretive Center
Lead architect Wyn Bielaska of Callison Architecture in Seattle
had quite a task in designing the multifunction Future of
Flight Aviation Center and Boeing Tour facility at Paine Field.
|
|
|
Building systems
in the Seattle Art museum expansion were designed for
flexibility.
(Rendering courtesy of NBBJ)
|
The project's 10-acre site was no easy flight, either.
Bielaska chose an innovative approach that not only blended
the building's diverse purposes - an aviation exhibit gallery,
a conference center, two gift shops, a 200-seat theater, a
tour facility and offices - but also emphasized the low green
hills and scenic vistas around the site.
He oriented the 63,000-sq.-ft. building on a sloping hillside
between a highway and the airfield's runway in a way that
offered the best views of the nearby Boeing 747, 767, 777
and 7E7 assembly plant; the airport; Mount Baker; and Mount
Rainier.
"The design of the building was primarily driven by
the site," the architect said. "The Museum of Flight
at Boeing Field in Seattle is in a sea of concrete. Paine
Field in Everett has rolling hills and mountain scenery. I
wanted to frame the building with the landscape and frame
(views of) the landscape from the building."
To eliminate retention ponds that would attract birds near
the runway, Bielaska worked with Erickson Landscape and Urban
Design of Seattle to use two innovative new products, GrassPave
and Rainstore. Together they dramatically reduce the amount
of necessary excavation, soil transporting, installation time
and labor that would have been required for retention ponds.
GrassPave uses open-ended plastic tubes buried a few inches
below the ground surface to catch water that would otherwise
flow off the site. Planting grass in the tubes allows water
to collect naturally, with improved drainage, and produces
a green surface. The tubes provide enough support to hold
together under the weight of vehicles.
"We'll use GrassPave for the aviation center's parking
areas instead of five acres of asphalt pavement," said
Bill Lewallen, the Snohomish County Airport's deputy director
for property management.
Similarly, Rainstore fills a large, excavated, underground
"retention pond" with recycled plastic formed into
sets of vertical tubes that capture and channel stormwater
into the storage space.
"Snohomish County is testing these two environmental
projects to evaluate how well they handle water runoff,"
Lewallen said. "Rainstore will enable us to substitute
underground storage for a surface-level retention pond."
Visitors will walk between earth berms and past a historic
737 tri-jet airliner as they enter the aviation center's lobby
at the north end of Beilaska's "square tube" hallway
that stretches from the lobby entrance to the Plaza of Planes,
a 102- by 268-ft. clear-span exhibit space.
At the south end of the corridor, he designed a deeply inset
window that frames the nose and cockpit of a giant 747 airliner
parked outside of the building.
"It will look much like the views of airliners you see
through an airport terminal window, but without any distracting
elements around it," Beilaska said. Looking back through
the hallway toward the lobby, that end of the "tube"
frames a view of Mount Baker and Cascade mountain scenery.
On the east side of the facility, paralleled by the Paine
Field runway, is the Boeing Tour Center, designed with bus
and vehicle parking, a gift shop and a 200-seat theater for
films shown prior to tours of the Boeing airliner assembly
plant. The café windows face west, overlooking the
727 exhibit and the multiroom convention center facilities
on the west side of the Plaza of Planes gallery.
Due to open in late August, the $22 million venture was initially
launched as the National Flight Interpretive Center. The facility
was renamed in December to more accurately reflect its unique
role among Pacific Northwest air museums.
Offering only a tip-of-the-hat to the past - represented
in the 747 and 727 Boeing aircraft displayed outside and a
few of the inside exhibits - the Future of Flight center is
designed to focus on present and future developments in airliner
manufacturing and technology.
|