|
University of Washington Activity
New Projects Complement Campus
Careful planning means renovations and new construction on the University of Washington's Seattle campus fit comfortably into the existing atmosphere.
by Sheila Bacon
According to an old saying, "The more things change,
the more they stay the same."
The same could be said for the University of Washington's
main campus in Seattle, where extensive renovations and new
construction projects are taking place, but within a defined
plan that seeks to preserve the nature of the campus and its
older buildings.
The University follows its own "historic buildings"
guidelines when renovating older structures, said Richard
Chapman, associate vice-president in the UW's capital projects
office. An architectural commission comprised of architecture
school leaders, university representatives and select architects
from throughout North America meets regularly to review project
drawings and talk to the community when change is imminent.
Johnson Hall is a good example of how history is preserved.
While the entire interior of this teaching facility is being
gutted and rebuilt, the only change the exterior will see
is the addition of an exit door at its south end.
The university is also sensitive to how new buildings compliment
the existing campus layout, said Chapman. New structures are
situated to respect existing view corridors to Mount Rainier
and Portage Bay. The siting of the new genome sciences and
bioengineering buildings west of the UW Medical Center not
only retain views of Portage Bay from the main campus, but
will also feature a large auditorium that captures views of
the waterway.
Construction activity currently underway includes a mix
of old and new, will all projects seeking to meld gracefully
into the UW's campus layout.
Johnson Hall
The presence of job trailers and a chain link fence may
be the only clue as to the activity underway at Johnson Hall,
a classroom and science teaching laboratory facility that
is undergoing an extensive interior renovation and seismic
upgrade. Built in 1928 with the addition of a wing in 1948,
the university has deemed Johnson Hall's ornate exterior appearance
worthy of preserving. Skanska USA Building (Seattle) crews
are completely gutting and rebuilding the interior of the
building, adding in new mechanical and electrical systems,
new elevators, upgraded restrooms and interior partitions.
 |
| Very little of the exterior of the University of Washington's Johnson Hall will change as crews upgrade the historic structure. The interior of the facility will be gutted and rebuilt, and the building will receive new mechanical and electrical systems as well as seismic upgrades.
( Photo by Sheila Bacon ) |
While larger restrooms and other upgrades will result in
the loss of five to 10 percent of usable interior space, the
new layout should make up for reduced program space.
"It will be a more efficient design than the original,"
said Chapman. "There are a lot of nooks and crannies
that weren't being efficiently utilized."
Construction work started in April, but Skanska, as the
project's general contractor/construction manager, was on
board much earlier. Skanska joined Seattle architects Arai
Jackson Ellison Murakami and the rest of the design team at
the beginning of the schematic design phase, said Chapman,
because the UW wanted a "true partnership" of all
team players.
It "paid dividends" to have Skanska's input on
constructability, sequencing and value engineering issues,
said Chapman. The university found success with the GC/CM
method during the renovation of the Suzzallo Library in 2001/02.
Turner Construction of Seattle joined the design team early
on to successfully complete seismic upgrades at the treasured,
80-year-old building. It was the first time the university
had used the method, said Chapman, and the university's board
of regents recently voted to use it again for the future renovations
of Architecture Hall and Guggenheim Hall.
When the $54 million, 121,5000-sq.-ft. Johnson Hall renovation
is completed in late 2006, the hall will feature classrooms,
labs a large lecture hall and faculty and staff offices.
Conibear Shellhouse
The new Conibear Shellhouse, a shell storage facility and
a training center for the UW's crew team, will replace the
old structure that was demolished last year. The new building
will feature 45,000 sq. ft. of space; considerably more than
the previous 28,000-sq.-ft. structure. The shellhouse's $16.9
million price tag is being funded through the university's
Intercollegiate Athletics department.
The ground level will house the storage facility and training
center, while the top floor's "academic center"
will be available for student athletes to study and dine.
 |
| The new Conibear Shellhouse
will offer student rowers an expanded facility. The façade
has been changed from the red shown here to green. ( Image courtesy of Miller Hull ) |
Sellen Construction (Seattle), the GC/CM, will complete
construction by next March, said Todd Lee, project manager
with Sellen Construction. The owner is expected to be moved
in and ready to open the facility by Opening Day of boating
season in early May.
With the project's location right on the edge of Lake Washington,
had to install a dewatering system to remove groundwater during
pile driving. Crews pumped from two feet below the water table
during excavation, said Lee, and the water table is just a
foot below the final slab-on-grade.
The UW crew team is continuing to launch from the dock just
east of the active construction site, said Lee, requiring
close coordination between both groups. Shells are being stored
on temporary racks installed near the site during construction.
Merrill Hall
The Center for Urban Horticulture's Merrill Hall is rising
again following the May 2001 arson that destroyed the building.
The $7 million, 18,000-sq.-ft. project - funded through a
combination of state funds, university monies and an aggressive
fundraising campaign - will closely match the previous facility.
Donations raised by the center's fundraisers will pay for
a new commons area and the administrative tasks required to
pursue LEED certification through the U.S Green Building Council.
The 2001 fire not only destroyed the building but also heavily
damaged books - many rare - in the center's attached library.
The new structure is using much of the old building's foundations
and will relocate the library within the facility. When complete,
it will again be used as teaching and lab space for students
in the Urban Horticulture program.
CDK is the project's general contractor and Miller Hull
is the architect. Construction completion of the stick-built
structure is expected in September.
Bioengineering and Genome Sciences Building
Once complete, this $150 million project will consolidate
the emerging bioengineering and genome sciences departments,
which are currently housed in numerous locations across campus.
The 265,000-sq.-ft. research and teaching building will also
feature a south-facing auditorium overlooking Portage Bay.
The five-story building attached to the existing UW Medical
Center via a walkway will open in phases. The bioengineering
portion will open at the end of 2005, with genome sciences
following in the first quarter of 2006.
Major program elements include wet research labs and shared
support space; vivarium; seminar and conference space; and
offices.
Because the building is constructed on a sloping site, it
touches the grade at three different levels, which form entries
at the north, midpoint and south ends. A continuous internal
"street" connects these entries and, consequently,
levels one, two and three. The building houses a café
with an external terrace facing Portage Bay.
Approval by the board of regents is still pending to expand
the West Campus Parking Garage by 300 stalls to accommodate
increased activity in the south campus area. Construction
job trailers currently occupy the future expansion space.
|
New Research and Technology Building
Constructed Using D/B/O/M
For the first time in the university's history, a design/build/operate/maintain
contract was awarded for a new project at the edge of
the UW campus.
The team of M.A. Mortenson of Bellevue, Wash., along
with CollinsWoerman of Bellevue and Johnson Controls
of Bothell, Wash., was awarded the D/B/O/M contract
at the UW Board of Regents May 20 meeting. The contract
will allow one entity to be responsible for the design,
construction, operation and maintenance of the building.
The structure, expected to be approximately 115,000
sq. ft., will be available to a variety of small departments
who need research space.
"We're approaching this as if we're a developer
and we're building a spec research building," said
Richard Chapman, associate vice-president in the UW's
capital projects office.
The university's goal is to provide space to university
departments at a cost comparable to space in the Seattle
area, but with the benefits and advantages of being
on a college campus.
"It's intended to be very versatile for any number
of schools doing research on campus," said Chapman.
The approximately $30 million shell and core will
be complete in late 2005, and tenant improvement will
be performed as the space is leased.
|
|