|
Portland International Airport
New Projects on Tap at PDX as Terminal Expansion South Improvements Complete
by Melody Finnemore
|
|
|
Part of Portland
International Airport's Terminal Expansion South project
included seismic upgrade work in the main terminal.
Photo courtesy of Hoffman
|
The recent completion of the Terminal Expansion South project
at Portland International Airport is expected to improve convenience
and comfort for the growing number of air travelers who pass
through PDX, as well as reflect the unique spirit of the Northwest
by showcasing some of the region's best artistic talent.
Phase III of the TES project, which began in April 2002,
involved the demolition of the old Concourse C and aircraft
control tower, the replacement of a remaining asphalt apron
between concourses C and D with concrete, the installation
of new storm drains and aircraft fueling system, and a complete
sewer connection for the north side of Concourse C.
An infill component of the expansion project added unfinished
shell space on the terminal's mezzanine level for office and
meeting room space, a "meeter/greeter" waiting area
on the main level that can be expanded into concession space
when future demand makes it necessary, and loading docks and
tenant storage space on the ground level.
In addition, the $38.6 million effort included the installation
of seismic bracing on all three levels of the terminal and
immediately adjacent portions of the building.
Overall, the project added more than 400,000 sq. ft. to the
lobby, concourse, ticketing and baggage processing space.
The new Concourse C replaced the 13 oldest gates in the airport
and provides travelers with wider passageways, waiting areas,
concessions and restrooms. It also creates a continuous, consistent
design that matches newer gates that were constructed in Concourse
C in 1998.
"These improvements collectively enhance our ability
to better meet the needs of the community for the next 10
to 15 years," said Steve Johnson, public affairs program
manager for the Port of Portland, which operates PDX.
Jim Dill, project manager for Portland's Hoffman Construction
Co., the general contractor on the Terminal Expansion South
project, said his greatest challenge was to ensure that construction
didn't interfere with the airport's operations. Construction
crews were charged with paving 350,000 sq. ft. - or eight
acres - of the apron during the brief window of opportunity
between spring and fall that Portland's weather allowed.
"The earthwork and the site work, because of the volume
of it and the short amount of time we had to do it, had the
potential for a lot of disruption and delays," Dill said.
"We ended up doing the excavation and backfill during
the day and pouring concrete at night, and we worked a lot
of double shifts."
An unknown amount of soil contaminated with airline fuel
also complicated matters. Some workers had been exposed to
contaminated soil while completing an earlier phase of the
Terminal Expansion South project, and planners wanted to ensure
it didn't happen again.
"On the TES III job we did an extra level of planning
to ensure the safe and efficient removal of what turned out
to be about 9,200 tons of soil that was contaminated by aviation
fuel," Dill said. "We took the (previous exposure)
as a lesson learned and did a lot of site work planning and
awareness planning way up front to make sure our workers were
educated and safe."
Tower Tumbles
|
|
|
A robotic
machine was used in the demolition of the old control
tower above the airport's main terminal.
Photo courtesy of Hoffman
|
One of the more unique aspects of the project involved the
demolition of the old control tower, a cast-in-place concrete
structure that stood 67 feet above the terminal roof and adjacent
to a Federal Aviation Administration office filled with vibration-sensitive
equipment.
"There was about 1,000 tons of material that had to
be removed within a three-month period," without harming
visitors in the airport's Oregon Marketplace or disrupting
24-hour operations at the FAA center, Dill said. "We
worked very closely with the demolition contractor to devise
a work plan that would accomplish this in the most effective
way possible, and the success of that portion of the project
is a credit to the subcontractor, Northwest Demolition."
Another unique element to the Terminal Expansion South project
is its emphasis on art. The Port of Portland Commission sought
the assistance of an arts advisory committee and the Regional
Arts and Culture Council in developing an art program for
the airport. Working with four Pacific Northwest artists,
the port commissioned an array of artwork that includes the
Columbia River inlaid in bronze into a terrazzo floor; benches
in the shapes of salmon, bridges and boats; and art poles
marking key spots along the Columbia River. Port of Portland
Commissioners wanted to set a precedent with this focus on
aesthetics in the terminal, Johnson said
"What we really want to do is reflect some of the beauty
and interesting culture that are so important in the Northwest,"
he said.
That strategy netted PDX an award in 2001 for the best overall
concessions program for medium-sized North American airports,
and will be a continuing theme as future improvements take
place throughout the airport.
Such long-range vision from the Port of Portland Commission,
amid changing administrations and industry trends, has been
key to the airport's success, according to Bob Frasca, partner
in charge of design at Portland's Zimmer Gunsul Frasca Partnership,
which has designed many of the improvements at PDX through
the last three decades.
"Even though the airport was built in small increments,
we didn't want it to look like it had been pieced together,
but instead it should look as though there was a singular
vision," Frasca said. "In the end, we were able
to achieve that. We do have a singular vision and this is
a 21st century building."
Long-term plans for Portland International Airport call for
improvements to Concourse A and the addition of a second parking
garage. The Port of Portland is in the very preliminary planning
stages for that project, which is scheduled for 10 to 15 years
down the road.
A more immediate change in store at PDX is the implementation
of an improved checked baggage screening system that will
replace the system put into effect shortly after Sept. 11,
2001. A mandated federal Aviation and Transportation Security
Act required all airports to provide explosion detection screening
of all checked baggage by Dec. 31, 2002. PDX met that requirement
by temporarily installing bag screening devices in the ticket
lobby. However, the large devices are bulky and their awkward
configuration has significantly cramped the space available
for travelers.
Construction should start in 2004 on the $50 million project,
which is intended to not only move screening equipment out
of the ticket lobby to create more space and comfort, but
also simplify the screening process for travelers.
"Currently, at our busiest time, we've almost maximized
our capacity in the ticketing lobby," Johnson said. "This
allows travelers to return to the old days when they handed
their bag to an airline representative and they were on their
way."
|