|
Oregon Health and Science University
Joint Venture Pairs Local GCs for Two Large Projects
by Sheila Bacon
|
|
|
Competing Portland general contractors
Hoffman Construction and Andersen Construction have
teamed up to build two large projects on the campus
of Oregon Health and Science University.
Image courtesy of OHSU
|
Two contractors who usually find themselves battling each
other for the big jobs have teamed up to build $321 million
in new construction at Oregon Health and Science University's
campus on Portland's Marquam Hill.
Hoffman Construction and Andersen Construction - both of
Portland - formed Hoffman/Andersen Joint Venture to tackle
the $105 million Biomedical Research Building and the $216
million Patient Care Facility.
The new projects are the first physical embodiments of the
university's Oregon Opportunity campaign, a public/private
fund-raising endeavor to support and expand OHSU's programs
and initiatives and to accelerate its biomedical research
activities.
Hoffman and Andersen have worked extensively on OHSU's campus
in the past, said Janine Stanton, the university's facilities
management and construction program director, but never before
as a team. However, both companies have worked on campus simultaneously
and have collaborated to coordinate site access and material
laydown.
"Hoffman has a lot of experience working on the hill and
with complicated sites, and Andersen has a huge amount of
experience working in our hospital," Stanton said. "I think
they'll bring to the table the best of both worlds."
The venture is a 60-40 partnership, said Bart Eberwein, Hoffman's
vice president of business development. Hoffman has sponsorship
of the job, and three team members from Hoffman and two from
Andersen comprise its executive committee. The decision to
partner increased both contractors' chances of working on
the project.
"We didn't think OHSU would award one contractor both projects,"
Eberwein said. "We'd rather work with a friend than an unknown."
|
|
|
Work on the
Patient Care Facility has started with construction
of the garage, requiring the closure of S.W. Campus
Drive, one of only two roads into and out of campus.
Image courtesy of OHSU
|
Construction on the Biomedical Research Building started
in February and will be completed in fall 2005. The 260,000-sq.-ft.,
11-story building will offer research laboratory and office
space, an advanced imaging research center and two floors
of comparative medicine.
The building was designed to help the university recruit
more of the nation's top researchers.
A skybridge will connect the new facility to the existing
outpatient clinic building in which many of OHSU's ambulatory
practices are currently located. The facility's architect
is Portland's Zimmer Gunsul Frasca.
Work on utility relocation for the Patient Care Facility
started in April, with mass excavation starting last month.
That project is expected to wrap up in late 2005 or early
2006. Also 11 stories, the 325,000-sq.-ft. building will house
144 inpatient beds, a
cardiac acute care unit, two oncology units, an intensive
care unit, an eight-room operating suite and an entire floor
dedicated to sterile processing to support all surgical services.
It features skybridge connections with OHSU Hospital and
a four-level, 456-space parking garage. Architecture firm
Perkins and Will of Los Angeles is working with associate
architects Peterson Kolberg and Associates of Portland.
The new structures join 50 other buildings on the campus.
OHSU educates health and high-technology professionals, scientists
and environmental engineers, and it undertakes the functions
of patient care, community service and biomedical research.
Various Challenges
The Biomedical Research Building is hemmed in on three sides
by existing outpatient and research facilities, while the
fourth side is a steep, heavily wooded hillside that drops
200 ft. to a road below.
"From an access standpoint, it's like building in a closet,"
said Bill Forsythe, program manager with Hoffman.
A rigorous, six-month planning phase focused on convincing
the city that the necessary removal of trees from the slope
would not cause erosion, Forsythe added. Builders agreed that
excavation of four levels of below-grade parking would be
done during the summer months before the fall and winter rains
set in. Crews kept to the tight schedule and had planned to
finish digging by the first of this month.
|
|
|
The 260,000-sq.-ft.,
11-story Biomedical Research Building will offer research
laboratory and office space; an advanced imaging research
center and two floors of Comparative Medicine.
Image courtesy of OHSU
|
The close proximity of the surrounding buildings necessitated
an interesting
placement of cranes. As usual, one sits in the middle of
the jobsite and is used to construct the building, but another
crane is located at the foot of the hill and is used to offload
delivered materials and swing them up to the jobsite.
Without this second crane, loads would have to be lifted
over occupied buildings; essentially forbidden in the city
of Portland.
Crews building the Patient Care Facility are currently focusing
efforts on the facility's parking garage, a job that requires
the temporary closure and relocation of S.W. Campus Drive,
one of only two roads into and out of campus. The road will
eventually reopen over the top of the parking garage, but
the work requires the street to be closed through April, funneling
student, staff and construction traffic to just one road.
While work begins on the garage, the design of a public tram
that will connect the OHSU campus to the developing South
Waterfront district is ongoing. The tram's terminus will be
located at the Patient Care Facility, although final designs
are not yet complete, nor are plans for how the terminus will
integrate with the facility.
While difficult terrain and tight sites make the construction
of OHSU's two new buildings complicated, the collaboration
between Andersen and Hoffman doesn't seem to pose much of
a challenge. Many of the project managers, superintendents
and crew members have worked together before or already know
each other from past jobs at OHSU, Forsythe said.
"It's almost like we're formalizing an informal partnering
that has been going on for years," he added.
The large footprint challenged builders
as well as designers. The building is much wider than it is
tall, so the construction schedule would not allow the entire
shell of the building to be enclosed before build-out began.
To keep on track, interior build-out had to start well before
the roof and exterior walls were in place, said Jeff Smith,
Turner Construction (Seattle) project superintendent. Last
winter, mechanical, electrical and plumbing rough-in crews
followed directly behind shell construction, working under
a temporary false roof that was created at every deck.
|