|
Portland State University’s Broadway
Housing
Creative Financing Speeds up Process
by Sheila Bacon
|
|
|
The University
of Portland used a unique financing method to build
the Broadway Housing student apartment complex.
Rendering courtesy of Otak
|
Portland State University is using a unique financing method
to shave months off the schedule for its new $47 million Broadway
Housing complex.
The arrangement will allow the university to occupy the new
384-unit student housing complex in September 2004 – a target
date that undoubtedly would have been missed had the university
used conventional financing methods.
Traditionally, universities need legislative approval for
funding of capital projects such as new dormitories, classrooms
or administrative buildings. The involvement of state government
often means the entire process – from concept to completion
– moves much slower than in a private developer scenario.
Here, the Broadway Housing project is owned by the Portland
State University Foundation, a 501(c)(3) corporation separate
from the university. It is being built to the university’s
specifications, but will be leased to the school by the foundation
upon its completion.
The foundation secured Portland’s Gerding/Edlen as its developer,
who brought architecture/engineering firm Otak and general
contractor Hoffman, both of Portland, on board. Key Bank was
chosen to sell the bonds. Because bids were solicited by the
foundation, not the school, use of the traditional low-bid
process was not necessary. And since the university is leasing
the property, not purchasing it, the Legislature’s involvement
was not required.
The result is an expedited procedure that will bring the
sizable project from concept to completion in just 23 months.
Under traditional methods, the entire process would have likely
taken at least three years, said Jay Kenton, PSU’s vice president
of finance and administration.
The university decided to use this alternative method of
developing the project precisely because it would be more
expeditious, Kenton added. Universities can only bring capital
items to the Legislature’s table at certain times. The land
for this project was up for sale and the foundation was able
to move quickly. An existing rapport between the developer
and the contractor resulted in a quick assembly of a project
crew.
“Most private developers in town said they couldn’t do it
as fast as we were doing it,” Kenton said.
The procedure also allows the foundation to own an asset,
ramps up its balance sheet and provides an outlet for it to
show its support for the university, Kenton added.
LEEDing the Way
The Broadway Housing complex at S.W. Jackson and S.W. Broadway
is a 10-story, approximately 220,000-sq.-ft. building offering
eight floors of student housing, one floor of academic space
and ground-level retail space. Although no retail leases are
yet signed, the university is considering locating a drugstore
and a restaurant or coffee shop in the space, Kenton said.
The project is seeking a Silver LEED rating by the U.S. Green
Building Council and will feature a large eco-roof that reduces
stormwater runoff. Other energy-saving features include increased
wall insulation, a condensing water heater, toilet exhaust
recovery, low-flow fixtures and condenser water pumping. Low-flow
fixtures and other investments will reduce water usage in
the building by 20 percent.
One-fourth of the building’s construction materials are locally
produced. Construction of Broadway Housing is on track to
be completed in August 2004, and students will be able to
move in the following month. Hitting that completion date
is critical, said Kenton.
He added that if the school had not used this quicker development
process, it’s unlikely the facility would be ready in late
summer, when the majority of students are making housing decisions,
and the university would have had to put the project off another
year, thus losing money on room leases.
PSU: On the Horizon
|