|
Everett Events Center
Fast-Moving Arena Used Design-Build Method
By Sheila Bacon
|
|
|
Construction of
the $72 million, 295,000-sq.-ft. Everett Events Center
in downtown Everett, Wash., wraps up this month, just
in time for the start of ice hockey season.
Rendering courtesy of LMN
|
Sometimes schedules are so critical to a job that missing
a key completion date could put the entire project in peril.
The Everett Events Center was one of those projects.
Construction of the $72 million, 295,000-sq.-ft. hockey arena
in downtown Everett, Wash., wraps up this month, just in time
for the start of ice hockey season. Well before designs were
even drawn, Nov. 15, 2003 loomed in the distance as the non-negotiable
date on which the arena had to be ready. Despite a major design
change and a week-long carpenters' union strike, crews have
kept the project on track and even expect to finish the building
at the beginning of this month - more than a month early.
Jamie Sipes, senior project manager for PCL Construction
of Bellevue, Wash., credited success under a tight, 17½ -month
construction schedule to the implementation of the design-build
method.
"If not for design-build, this probably wouldn't have been
built," he said.
If PCL crews had to wait until the design was complete to
bid on the project, Sipes figures it would have taken an extra
four months to build, setting the completion date far beyond
the start of hockey season.
The arena is located on two city blocks between Hewitt and
Wall streets and Broadway and Oakes avenues. The facility
will host minor league hockey, conventions, concerts, exhibitions,
rodeos and trade shows. The Everett Silver Tips, the Western
Hockey League's newest team, will be the 8,250-seat arena's
anchor tenant. An attached community ice sheet will be available
for use by the general public.
Depending on the season, both ice sheets can be covered or
melted to offer 58,000 sq. ft. of contiguous space for exhibitions
or trade shows. Seating is removable and retractable to offer
a larger and more flexible space.
|
|
|
The Everett
Events Center's 8,250-seat arena is where the city's
new ice hockey team - the Everett Silver Tips - will
play.
Photo courtesy of LMN
|
Added late in the design phase is a three-floor, 50,000-sq.-ft.
conference center featuring a 12,000-sq.-ft. ballroom, prefunction
space, meeting rooms, offices and ground-level retail. The
space - attached to the north side of the community ice sheet
- was an option added in when the project was well into the
design document phase.
The change in plans also included a modified façade for the
entire project - one that included more brick to blend easier
with the arena's historical surroundings. The revisions increased
the project cost by 25 percent, sent designers back to the
drawing board and cut into PCL's original 20-month construction
schedule by two months.
Work on the project was kept on track thanks to favorable
weather during the critical earthwork and roof erection, and
a lot of teamwork.
"At the time (the addition of the conference center) looked
to be an enormous challenge," said Fred Safstrom, executive
director of the Everett Public Facilities District, the agency
overseeing the creation of the arena. "PCL took it on and
not only achieved it, but will be finishing a month early."
Saving Time and Money
That spirit of teamwork began taking shape early on in the
design-build process. By working closely with architects LMN
of Seattle and PBK of Vancouver, B.C., as well as structural
engineering firm Magnusson Klemencic of Seattle, PCL was able
to offer a number of time- and money-saving options.
For example, PCL worked closely with the structural engineers
in the design of the precast forms. A design system was created
to match some of PCL's own interior forming systems. By using
existing forming systems instead of building new ones, Sipes
estimated the owner was saved hundreds of thousands of dollars.
PCL even involved its subcontractors in many of its design-build
processes. Precast sub Bethlehem Construction of Cashmere,
Wash. was invited to share its expertise during design meetings
so the building system could be further value engineered.
Like Seattle's Space Needle or Tacoma's Dome, the Everett
Events Center may soon become the facility that identifies
the city. The roof structure features a suspension bridge-style
support system with 200-ft. masts that reduces the need for
view-blocking columns inside the arena and also adds a recognizable
icon to the city's skyline.
The event center's design is the result of a design-build
competition sponsored by the city of Everett's Public Facilities
District. Of 10 entries, the LMN/PBK/PCL project team was
one of three chosen to further detail its design. It was ultimately
chosen as the winning team.
The entry was the only design that was able to offer the
community ice sheet portion of the work for the allocated
budget.
Tom Burgess, LMN project manager, said the team's considerable
attention to the organization of the arena on the sloped site
was one reason enough money could be saved to provide the
second sheet of ice - an option that was important to the
owner. He said the design allows entry to the arena in a natural
way, taking advantage of the site's contours instead of implementing
costly escalators and other people-movers.
The distinctive cable-stayed roof design allowed the design
team to use an efficient structural system, bringing the roof
plane lower and lessening the truss depth, Burgess said.
Team Effort Scores at Everett
Events Center
|