Marion Oliver McCaw Hall Readies For Debut
by Dale Simpson
 |
While providing spacious
accommodations for audiences and performers, Marion Oliver
McCaw Hall proved to be a restricted work area for Skanska
and their subcontractors.
Image Courtesy of Skanska |
The effort to create a world class facility where a 1920's
performance hall and hockey rink once stood wrapped in early
June with a flurry of last-minute activity to ready the new
venue for its opening ceremonies on June 28. The Mercer Arena
had been transformed from a hockey rink into the 60,000-sq-ft.
Mercer Arts Arena, and the new Marion Oliver McCaw Hall stood
proudly in the place once occupied by the Seattle Opera Hall.
Throughout the $125 million construction effort that began
in 2001 major tenants - Pacific Northwest Ballet and Seattle
Opera - performed on schedule. The bustling Seattle Center
continued to host dozens of events on its adjoining 62-acre
campus that includes the Experience Music Project.
To accomplish this feat, general contractor/construction
manager Skanska (Seattle) and the Seattle Center undertook
a $7 million renovation to convert the Mercer Arena into a
temporary venue for the opera and ballet. This effort involved
removing the arena's lower seating and digging 5-ft. below
grade to create an orchestra pit, adding a stage, a new seating
bowl and replacing old electric and heating systems.
With the task of providing a temporary performance venue
complete, Skanska and its team turned their attention to the
major task, creating a world-class performance hall on the
site formerly occupied by a facility that could no longer
serve the needs of its community.
About 75 percent of the original structure was rebuilt after
completely gutting its interior. Other improvement include
a seismic upgrade; adding view boxes with improved sight lines
in the auditorium, new heating and new electrical systems,
a new lobby boasting a spectacular curtain wall, and a new
landscaped promenade that opens the Seattle Center campus
up to Mercer Street and the International Fountain.
Skanska was on board early on in the process, working closely
with the design team 18 months before renovation work on the
Mercer Arena started in 2001. Still, the project's schedule
needed tweaking in order to delivered on time, on schedule
and on budget.
Construction and Theater Artistry
The initial schedule called for work to start on the main
opera hall in January 2002 - after the ballet troupe's popular
holiday production of the "Nutcracker" had ended.
However, Skanska identified a number of jobs that could be
completed in the basement of the opera house earlier on in
the process. The contractor persuaded the owner to approve
an "early works" package that essentially gave the
construction team early entry into the facility and a 4-month
head start on the project.
Early work included installing of underground utilities,
investigation of existing site conditions, adding support
columns to carry the new loads, adding steel beams under the
auditorium, and shoring under the future promenade to support
demolition contractor Nuprecon's (Snoqualmie, Wash.) heavy
machinery. This crucial work was accomplished between performances
while the opera and ballet troupes were still occupying the
hall.
Although the "early work" comprised just five percent
of the total job, it made a big impact in the way the crews
proceeded. Combining work in the arena with the early work
in the opera hall was approved by the owner only after Seattle
Center representatives were convinced that the job's schedule
required it, and that the hall's users would not be affected.
Initial concerns were coordinating potentially disruptive
construction work around opera and ballet performances; as
well as the fact that the early work would require around
$6 million in funds earlier than the original schedule had
anticipated. Those fears were quelled when Skanska presented
a detailed work schedule and the funds were made available
for use earlier. "Seattle Center's willingness to work
out an early access plan is a major reason we were able to
be on time an on budget with the project," says Scott
Lee, Skanska Washington Division vice president.
New Additions
MOM Hall's upgrades will benefit performers as well as its
audience. Performers will enjoy a new 4,000-sq.-ft. rehearsal
space, six vocal coaching rooms with acoustical isolation,
a 750-sq.-ft. reception room, a 1,000-sq.ft. wardrobe room,
a 1,200-sq.-ft. make-up and wig room, a 900-sq.-ft. musician's
lounge and a world-class staging facility.
The public accommodations feature twice the number of women's
restrooms and family restrooms throughout the building. A
750-sq.-ft. second balcony lobby offers expansive views of
the Seattle Center grounds. A new public café on the
south side of the lobby opens onto outdoor seating facing
the Seattle Center.
The auditorium sides have been brought in slightly, narrowing
the space and making for a more cozy setting for the audience.
Existing balconies were replaced with side boxes providing
improved sight lines, similar to the Seattle Symphony's Benaroya
Hall. Rear balcony extensions compensate for seats removed
at stage level. Elevated seating sections along each side
of the orchestra level sweep down to the stage from the first
balcony so that many audience members will be seated eye-level
with the stage.
The goal of LMN Architects (Seattle) was to create a sense
of intimacy between the audience and the performers; a key
component of a world-class venue.
A taller fly loft - the space above the stage used for equipment
that raises and lowers sets - adds more clearance area and
allow stage hands to more easily handle large sets. A new
loading dock, with a 40-ft. by 40-ft. entry at stage level,
allows the ballet and opera to use props and stage displays
borrowed from other troupes around the country - something
the groups had been unable to do before. The old venue's 12-ft.
by 16-ft. stage door and insufficient loading dock meant some
sets had to be turned away because they wouldn't fit through
the doors.
Few visitors will notice the complete seismic upgrade, with
additional steel framing and concrete shear walls located
discreetly throughout the building.
All new lighting and HVAC systems installed by CDi Engineers
(Lynnwood, Wash.) features a unique displacement ventilation
system, which introduces cool air into the auditorium at seat
level. The innovative design - which is used frequently in
Europe but only recently at performance halls in the United
States - is both energy and cost efficient.
Electrical engineering firm Sparling's (Seattle) designs
consist of a completely new electrical system throughout the
hall. Project highlights include additional power connections
throughout the auditorium and lobby to support activities
such as Bumbershoot performances. Previously, Seattle Center
crews had to rig extension cords and perform considerable
prep work to be able to accommodate these one-time acts. Other
Sparling designs include a system that supports television
screens in the lobby, lecture hall and donor rooms, so latecomers
can view the performance while they wait to enter the hall
during an intermission.
Clearly Spectacular
Possibly the most dramatic part of MOM Hall is its new grand
entry and courtyard area. A serpentine-shaped, ultra-clear
glass curtainwall - measuring 60 ft. tall and more than 200
ft. long - will enclose the lobby.
Large metal fabric "scrims" will attach to the
glass curtainwall, onto which colored light will be projected.
The design of the curtainwall was one of several challenges
faced by Seattle structural engineer Skilling Ward Magnusson
Barkshire. The design went through much iteration as SWMB
and LMN worked together to ensure the glass wall was both
visually striking and structurally sound.
Engineers studied wind load, wall tension and the rigidity
of the supporting roof, among many other issues. This careful
attention to detail helped along with the ability to fabricate
panels in-shop helped Walters and Wolf complete installation
in just five weeks.
The landscaped courtyard designed by Seattle's Gustafson
Partners, opens up the space between Mercer Street and the
Seattle Center, providing a welcoming connection for the public
that had never existed before. The area includes an expansive
water feature and landscaped planters, and will also incorporate
the existing tall trees bordering the Seattle Center.
The hall's lobby has undergone a dramatic transformation.
The old lobby consisted of a series of separate, single-story
spaces tucked in between an old seating bowl that that had
been encapsulated years ago. Demolition crews completely removed
the seating bowl and existing lobby spaces, resulting in an
open lobby space through all primary floor levels.
Community Support
The renovation is a public/private partnership merging public
support of $55 million with private gifts of $70 million.
The bulk of the private donations - $20 million - came from
brothers Bruce, Craig, John and Keith McCaw in honor of their
mother, Marion Oliver McCaw Garrison, a long-time supporter
of the arts in the Northwest and an opera enthusiast. The
fundraising campaign continued through June 2003.
Support for MOM Hall has extended beyond the donor community.
The hall's users and staff; the design community; and the
local Queen Anne area neighbors have all been supportive of
the project.
Following June 28 opening celebration, the Seattle Opera
moves in and readies the hall for its first performance August
12. Next, the Pacific Northwest Ballet will begin preparations
for its 2003-2004 season. Bravo.
|