Sun Rises On Sunset Interchange
$20 million over budget, I-90
interchange set to open soon
By Matt Villano
 |
Precast concrete
ramp panels feature distinctive leaf patterns that complement
the adjacent wooded foothills.
Photo courtesy of Kiewit. |
Ask any Eastside commuter about the morning backups from
downtown Issaquah onto Interstate 90 and you're bound to hear
moans about sitting in traffic for 40 minutes to drive no
more than 2 miles. Eastside communities groaned even more
when Microsoft announced plans to build a new campus on the
Sammamish Plateau north of the Front Street exit.
Luckily, the Washington State Department of Transportation
followed Microsoft with an announcement of its own. It planned
to build a $176 million interchange to ease area congestion
overall. The new Sunset Interchange was designed to incorporate
bridges and flyovers to shuttle traffic on and off the freeway
more smoothly.
After two years and tens of millions of dollars in change
orders, Sunset is set to open on schedule in August.
"The project didn't come in on budget, but it's a real
testament to the people working on it that we were able to
get the job done on time," said Ann Hegstrom, project
manager for the Pacific Building Division of Omaha- based
Kiewit Construction Co., which serves as general contractor
on the job.
The interchange will span nearly 25 acres, including more
than 2 miles of new exit ramps, 104,000 cubic meters of earthwork
and four new bridge structures connecting Issaquah to the
south with the Sammamish Plateau and Issaquah Highlands to
the north.
The bridges are the highlight of the project, including a
925-ft. twin steel-tub flyover, a precast, post-tensioned
concrete-tub undercrossing, another twin steel tub structure
with a girder span that has the distinction of being the longest
structure ever hauled on a Washington State highway and a
1440-ft. concrete box girder structure.
The interchange also boasts a number of MSE structural walls,
as well as soldier pile walls with tiebacks constructed to
allow for on and off-ramps on either side of the highway.
All of the MSE walls have precast concrete panels with a distinctive
floating-leaf pattern.
The leaves though a bit unusual, stand out from the freeway
corridor like a bas-relief painting and give the interchange
an artsy appearance.
Mark Hinthorne, Issaquah's planning director, said the interchange
will improve things fairly soon after it opens. "People
will shift their driving patterns to take advantage of it,
and in the end, that's all we can hope for," he added.
Project Challenges
From its beginning in April 2001, the Sunset job presented
a number of challenges.
First, Hegstrom said was the need to plan and schedule installation
of the undercrossing and steel-tub flyover spanning I-90.
This made it necessary to close the freeway to traffic. Because
of heavy volumes, closures could only be from 11:00 P.M. to
5:00 A.M.
Next, during earth moving and drilling operations, Kiewit
and its subcontractors discovered unforeseen site conditions.
Among them was a preexisting landslide and car-sized underground
granite boulders that precluded normal drilling. Overcoming
these hurdles cost the project contractor six months and led
to nearly 100 change orders totaling nearly $25 million.
In order to drill shaft foundations, Seattle-based Malcolm
Drilling Co. brought in European oscillating drill rigs.
Changing the shaft required changing the column size, which
in turn changed the hammerhead crossbeams, the bearings and
the connections for the steel-tub girders.
In the end, Kiewit and the subcontractors were successful;
in some cases drilling column shafts of up to 100 ft. deep
and 12 ft. wide. However, the project had been delayed six
months.
The job also has presented logistical challenges for the
Washington Department of Transportation in that it has had
six funding partners. In addition to WSDOT, they are:
- Port Blakely Communities
- King County
- City of Issaquah
- Federal Highway Administration
- Transportation Improvement Board
- Sound Transit
WSDOT project engineer Matt Preedy said that although this
kind of cooperation and teamwork is difficult to pull off,
doing it successfully "has given us a good look into
what the future holds." He was referring to future projects
involving widening of Interstate 405 and the floating-bridge
replacement on state route 520.
"All of these large-scale jobs will require interagency
coordination, and this job is a good case of showing that
we can deliver these sorts of projects with all these involvements,"
Preedy added.
Practical Challenges
The waters of Issaquah Creek also had to be protected.
The salmon-spawning stream runs along the southern boundary
of the Front Street off-ramp, then turns north and passes
beneath the bridge and flyover of the interchange.
Permitting conditions allow access to the creek only from
June 15 to Sept. 15. The creek is inaccessible at other times
in order to preserve the fragile ecosystem.
Hegstrom said the project spent nearly $1.5 million on temporary
erosion control.
This was a complicated contracting task. There were 11 material
suppliers and subcontractors in all, including Tacoma-based
Concrete Technology Inc. for the pre-stressed girders; San
Diego-based L.B. Foster Co. for the MSE wall panels; Seattle--based
Harvard Steel for the rebar; Vancouver-based USI for steel
girders; Redmond-based Watson Asphalt Paving Co. Inc. for
the asphalt paving and Kent-based Signal Electric.
Looking ahead
Project engineer Preedy and his colleagues said the project
is far from over.
After the interchange opens in August, planning currently
underway will continue. First priority: a City of Issaquah
$40 million southeast bypass that establishes a direct route
connecting I-90 to Issaquah-Hobart Road to the south, circumventing
downtown.
There is also work planned to the north, in and around the
future 150-acre Microsoft campus. This work should be finished
by 2007 or 2009, and in addition to new office space, should
consist of 3,200 homes and other retail locations.
|